2016-02 Modifications to CIP Standards | CIP-003-7, Implementation Plan, and definiton of TCA and Removable Media

Description:

Start Date: 12/12/2016
End Date: 01/25/2017

Associated Ballots:

Ballot Name Project Standard Pool Open Pool Close Voting Start Voting End
2016-02 Modifications to CIP Standards CIP-003-7(i) Non-binding Poll IN 1 NB 2016-02 Modifications to CIP Standards CIP-003-7(i) Non-binding Poll 07/21/2016 01/10/2017 01/16/2017 01/26/2017
2016-02 Modifications to CIP Standards CIP-003-7(i) IN 1 ST 2016-02 Modifications to CIP Standards CIP-003-7(i) 07/21/2016 01/10/2017 01/16/2017 01/25/2017
2016-02 Modifications to CIP Standards Transient Cyber Asset | New Definition IN 1 DEF 2016-02 Modifications to CIP Standards Transient Cyber Asset | New Definition 07/21/2016 01/10/2017 01/16/2017 01/25/2017
2016-02 Modifications to CIP Standards Removable Media | New Definition IN 1 DEF 2016-02 Modifications to CIP Standards Removable Media | New Definition 07/21/2016 01/10/2017 01/16/2017 01/25/2017
2016-02 Modifications to CIP Standards CIP-003-7(i) Implementation Plan IN 1 OT 2016-02 Modifications to CIP Standards CIP-003-7(i) Implementation Plan 07/21/2016 01/10/2017 01/16/2017 01/25/2017

Filter:

Hot Answers

In the current TCA definition, section 4, first bullet:  If the intent of the definition for “BES Cyber Asset” to be applicable for all three impact classifications (High, Medium, and Low), then SDG&E recommends adding this clarification.

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Other Answers

Jamie Monette, Allete - Minnesota Power, Inc., 1, 1/9/2017

- 0 - 0

RoLynda Shumpert, On Behalf of: SCANA - South Carolina Electric and Gas Co., SERC, Segments 1, 3, 5, 6

- 0 - 0

Christopher Chavez, On Behalf of: Salt River Project, WECC, Segments 1, 3, 5, 6

- 0 - 0

MRO NSRF, Segment(s) 3, 4, 5, 6, 1, 2, 1/4/2017

- 0 - 0

Bobby Olsen, Salt River Project, 6, 1/19/2017

- 0 - 0

Dennis Minton, On Behalf of: Dennis Minton, , Segments 1, 3

- 0 - 0

Sarah Gasienica, 1/19/2017

- 0 - 0

- 0 - 0

Michael Ward, 1/20/2017

- 0 - 0

Tennessee Valley Authority, Segment(s) 1, 3, 5, 6, 9/1/2016

- 0 - 0

Sean Bodkin, Dominion - Dominion Resources, Inc., 6, 1/23/2017

- 0 - 0

Seattle City Light has concerns that the revised definition of Transient Cyber Asset is not consistent with the risk-based approach reflected in the NERC CIP version 5/6 Standards. In particular Seattle finds the revised definition is inconsistent with the language of CIP-002-5.1 R1.3 regarding identification of BES Cyber Systems (and by extension BES Cyber Assets) at Low impact facilities, specifically that: “a discrete list of low impact BES Cyber Systems is not required.” Given that the proposed definition defines Transient Cyber Assets in terms of BES Cyber Assets and BES Cyber Systems, Seattle does not understand how the existence of any low impact Transient Cyber Asset can be documented or audited absent a list of such BES Cyber Systems or Assets. Seattle is further concerned that the revised definition could lead to a requirement to produce such lists, which previously has been deemed not consistent with the risk-based approach adopted in CIP version 5/6 (because the development and accurate maintenance of such lists would consume large resources that would provide greater benefits to cyber security if applied elsewhere). At this time Seattle does not have alternative language to suggest to resolve this conundrum, which is inherent to the structure of CIP version 5/6. Perhaps a revision of the definition for Low impact Transient Cyber Asset to reference only a temporary connection “to a BES Cyber System at a low impact facility” might work, but Seattle remains unconvinced that such a definition would prove auditable.

Ginette Lacasse, On Behalf of: Seattle City Light, WECC, Segments 1, 3, 4, 5, 6

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Ryan Olson, Portland General Electric Co., 5, 1/23/2017

- 0 - 0

The proposed definition of Transient Cyber Asset (TCA) implies additional requirements for entities to comply with that is in misalignment with standards that are currently approved and in effect. The purpose of CIP-003-7(i) is to create TCA requirements for Low Impact BES Cyber Systems, yet none of the criteria of item 4 of the definition can be achieved for Lows without imposing additional, and improper, requirements upon the Registered Entities. Item 4 bullets 2 and 3 are omitted because they explicitly require the device or network to be associated with a high or medium impact, leaving just the direct connection to a BES Cyber Asset as the required #4 criteria. However, CIP-002-5.1 R1.3 reads “Identify each asset that contains a low impact BES Cyber System according…if any (a discrete list of low impact BES Cyber Systems is not required).” The requirement explicitly states that a discrete list of BES Cyber Systems is not required. BES Cyber Systems are defined as “One or more BES Cyber Assets logically grouped”, showing that BES Cyber Assets are a sub-componet of a BES Cyber System. CIP-002-5.1 explicitly states that a list of low impact BCS is not required, yet this definition of TCA would require entities to evaluate and inventory, and maintain that inventory, to identify every BES Cyber Asset in order to correctly identify TCA that could be used at a low impact site. Entergy proposes some verbiage to include low impact BCS, while not adding additional inventorying requirements such as “Anticipated for use within a low impact BCS, if any”.

Julie Hall, Entergy, 6, 1/23/2017

- 0 - 0

Daniel Gacek, Exelon, 1, 1/23/2017

- 0 - 0

Aaron Cavanaugh, On Behalf of: Bonneville Power Administration, WECC, Segments 1, 3, 5, 6

- 0 - 0

Luminant, Segment(s) 6, 7, 5, 1/24/2017

- 0 - 0

Maryclaire Yatsko, On Behalf of: Seminole Electric Cooperative, Inc., FRCC, Segments 1, 3, 4, 5, 6

- 0 - 0

Request that the guidance be added to the Guidance and Technical Basis (GTB) on the need for the additional language referencing High and Medium Impact with regard to ESP’s and PCA’s to the Transient Cyber Asset definition.  Guidance would show that low impact BES Cybers Systems may be configured in a way that would meet the definition of ESP even though an ESP is not required or been identified.

Colorado Springs Utilities, Segment(s) 5, 3, 1, 6, 5/6/2015

- 0 - 0

Jason Snodgrass, 1/24/2017

- 0 - 0

Duke Energy would like to point out a possible typo on page 3 of the Proposed Definitions of: Transient Cyber Asset”(TCA) and “Removable Media” document. The title of the section on page 3 reads “Currently Approved Definition of Transient Cyber Asset (TCS)”. The definition below is actually the definition of Removable Media. The title appears to be incorrect. We recommend the drafting team change the title to read: “Currently Approved Definition of Removable Media”.

Duke Energy , Segment(s) 1, 5, 6, 4/10/2014

- 0 - 0

Illinois Municipal Electric Agency supports comments provided by the American Public Power Association.

Bob Thomas, 1/25/2017

- 0 - 0

Lan Nguyen, On Behalf of: CenterPoint Energy Houston Electric, LLC, Texas RE, Segments 1

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Aaron Austin, On Behalf of: AEP, SPP RE, RF, Segments 1, 3, 5, 6

- 0 - 0

Jeffrey DePriest, 1/25/2017

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

- 0 - 0

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

David Gordon, 1/25/2017

- 0 - 0

Since PCA is already defined by NERC, NRG recommends deleting associated with high or medium impact BES Cyber Systems since “associated” could be misunderstood and appears to be redundant. For example, would a VPN connection be considered a TCA? (i.e. connecting at layer 3 or below)

Kara White, On Behalf of: NRG - NRG Energy, Inc., FRCC, MRO, WECC, Texas RE, NPCC, SERC, SPP RE, RF, Segments 3, 4, 5, 6

- 0 - 0

  1. We feel the SDT’s approach to revise the definition of Transient Cyber Assets (TCA), such that it is relevant to the controls required for high, medium, and low impact BES Cyber Systems, is inconsistent with the directives listed within FERC Order No. 822.  These directives focus on the high and medium impact BES Cyber Security requirements.  However, the proposed revisions implicitly require low impact entities to have the same level of risk mitigations in places as if they were associated with high and medium impact BES Cyber Systems.  We believe the SDT should avoid the inclusion of low impact BES Cyber Systems entirely or provide proof of a risk analysis to substantiate this activity.
  2. The SDT’s proposed approach will also create difficulty for industry to demonstrate compliance since a BES Cyber System’s inventory list is not required for low impact entities.  How are auditors able to benchmark a low impact entity’s compliance program without a current list?
  3. We suggest the SDT consider another method to address the FERC directive that still preserves the low impact requirements and the explicit exclusion from being required to have an inventory list of low impact assets.  Such an approach could include TCAs in the technical guidance under Electronic Access Controls.
  4. Another possible approach is for low impact entities to have a documented process that applies electronic access controls for TCAs to low impact assets.
    1. Auditors could verify that the entity has developed the documented process, and the entity could demonstrate compliance by providing the document as evidence.
    2. This approach also preserves the disparate treatment of low and medium impact assets by assigning different requirement levels that commensurate with BES level risks.

ACES Standards Collaborators, Segment(s) 1, 5, 3, 4, 1/25/2017

- 0 - 0

Mike Anctil, 1/25/2017

- 0 - 0

Tacoma Power supports comments submitted by APPA.

John Merrell, Tacoma Public Utilities (Tacoma, WA), 1, 1/25/2017

- 0 - 0

Add a « Low impact BES » item in the TCA definition. This will exempt the inventory requirement for low to demonstrate compliance for the TCA.

The proposed definition of a Transient Cyber Asset (TCA) is:

A Cyber Asset that is:

1.   capable of transmitting or transferring executable code,

2.   not included in a BES Cyber System,

3.   not a Protected Cyber Asset (PCA) associated with high or medium impact BES Cyber Systems, and

4.   directly connected (e.g., using Ethernet, serial, Universal Serial Bus, or wireless including near field or Bluetooth communication) for 30 consecutive calendar days or less to a:       

BES Cyber Asset,

Add "Low impact BES Cyber System”,

network within an Electronic Security Perimeter (ESP) containing high or medium impact BES Cyber Systems, or

PCA associated with high or medium impact BES Cyber Systems.

Roger Dufresne, 1/25/2017

- 0 - 0

It would be helpful if the revised definitions could be reorganized to provide the inclusions first and the exclusions second to make them easier to read and implement. For example, the TCA definition could be changed to:

“A Cyber Asset that is: 1) capable of transmitting or transferring executable code; 2) directly connected (e.g., using Ethernet, serial, Universal Serial Bus, or wireless including near field or Bluetooth communication) for 30 consecutive calendar days or less to a: BES Cyber Asset, network within an Electronic Security Perimeter (ESP) containing high or medium impact BES Cyber Systems, or PCA associated with high or medium impact BES Cyber Systems; 3) not included in a BES Cyber System; and 4) not a Protected Cyber Asset (PCA) associated with high or medium impact BES Cyber Systems. Examples...”

Also, the applicability of the definitions to LIBCS is not clear, we recommend changing “BES Cyber Asset” in bullet 4 for each definition to “BES Cyber System” or alternatively “low, medium, or high impact BES Cyber System.”

Melanie Seader, On Behalf of: Edison Electric Institute, NA - Not Applicable, Segments NA - Not Applicable

- 0 - 0

Suggest to add a « Low impact BES » item in the TCA definition. This will exempt the inventory requirement for low to demonstrate compliance for the TCA.

The proposed definition of a Transient Cyber Asset (TCA) is:

A Cyber Asset that is:

1.   capable of transmitting or transferring executable code,

2.   not included in a BES Cyber System,

3.   not a Protected Cyber Asset (PCA) associated with high or medium impact BES Cyber Systems, and

4.   directly connected (e.g., using Ethernet, serial, Universal Serial Bus, or wireless including near field or Bluetooth communication) for 30 consecutive calendar days or less to a:

  • BES Cyber Asset,

  • Add “Low impact BES Cyber System”,

  • network within an Electronic Security Perimeter (ESP) containing high or medium impact BES Cyber Systems, or

  • PCA associated with high or medium impact BES Cyber Systems.

Si Truc Phan, On Behalf of: Hydro-Qu?bec TransEnergie, NPCC, Segments 1

- 0 - 0

Wendy Center, U.S. Bureau of Reclamation, 5, 1/25/2017

- 0 - 0

Amy Casuscelli, On Behalf of: Xcel Energy, Inc. - MRO, WECC, SPP RE - Segments 1, 3, 5, 6

- 0 - 0

Santee Cooper agrees with APPA's comment/concern. 

Santee Cooper , Segment(s) 1, 5, 1/25/2017

- 0 - 0

Rachel Coyne, Texas Reliability Entity, Inc., 10, 1/25/2017

- 0 - 0

Patricia Lynch, 1/25/2017

- 0 - 0

Patricia Lynch, 1/25/2017

- 0 - 0

Request that the guidance be added to the Guidance and Technical Basis (GTB) on the need for the additional language referencing High and Medium Impact with regard to ESP’s and PCA’s to the Transient Cyber Asset definition.  Guidance would show that low impact BES Cybers Systems may be configured in a way that would meet the definition of ESP even though an ESP is not required or been identified.

FMPA, Segment(s) , 12/5/2016

- 0 - 0

SPP Standards Review Group, Segment(s) , 1/25/2017

- 0 - 0

Southern Company, Segment(s) 1, 3, 5, 6, 8/3/2016

- 0 - 0

RSC no Dominion and OPG, Segment(s) 1, 0, 2, 4, 5, 6, 7, 3, 1/20/2017

- 0 - 0

- 0 - 0

Sandra Shaffer, Berkshire Hathaway - PacifiCorp, 6, 1/25/2017

- 0 - 0

Request that the guidance be added to the Guidance and Technical Basis (GTB) on the need for the additional language referencing High and Medium Impact with regard to ESP’s and PCA’s to the Transient Cyber Asset definition.  Guidance would show that low impact BES Cybers Systems may be configured in a way that would meet the definition of ESP even though an ESP is not required or been identified. The definition does not spell out what defines a TCA in a low impact environment.  Should the definition include additional instruction related to item 4 such as “connected to a cyber asset located in an asset contiaing low impact BES Cyber Systems”?

Ronald Donahey, TECO - Tampa Electric Co., 3, 1/25/2017

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Hot Answers

In the proposed Removable Media definition, section 4, first bullet:  If the intent of the definition for “BES Cyber Asset” to be applicable for all three impact classifications (High, Medium, and Low), then SDG&E recommends adding this clarification.

 

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Other Answers

Jamie Monette, Allete - Minnesota Power, Inc., 1, 1/9/2017

- 0 - 0

RoLynda Shumpert, On Behalf of: SCANA - South Carolina Electric and Gas Co., SERC, Segments 1, 3, 5, 6

- 0 - 0

Christopher Chavez, On Behalf of: Salt River Project, WECC, Segments 1, 3, 5, 6

- 0 - 0

MRO NSRF, Segment(s) 3, 4, 5, 6, 1, 2, 1/4/2017

- 0 - 0

Bobby Olsen, Salt River Project, 6, 1/19/2017

- 0 - 0

Dennis Minton, On Behalf of: Dennis Minton, , Segments 1, 3

- 0 - 0

Sarah Gasienica, 1/19/2017

- 0 - 0

 

The term “transferring code” is misleading because the device itself (for example, storage media) cannot transfer code without assistance from the host computer.

 

- 0 - 0

Michael Ward, 1/20/2017

- 0 - 0

Tennessee Valley Authority, Segment(s) 1, 3, 5, 6, 9/1/2016

- 0 - 0

Sean Bodkin, Dominion - Dominion Resources, Inc., 6, 1/23/2017

- 0 - 0

As is the case for the revised Transiet Cyber Asset definition, Seattle City Light has concerns that the revised definition of Removable Media is not consistent with the risk-based approach reflected in the NERC CIP version 5/6 Standards. In particular Seattle finds the revised definition is inconsistent with the language of CIP-002-5.1 R1.3 regarding identification of BES Cyber Systems (and by extension BES Cyber Assets) at Low impact facilities, specifically that: “a discrete list of low impact BES Cyber Systems is not required.” Given that the proposed definition defines Removable Media in terms of BES Cyber Assets and BES Cyber Systems, Seattle does not understand how the existence of any low impact Removable Media can be documented or audited absent a list of such BES Cyber Systems or Assets. Seattle is further concerned that the revised definition could lead to a requirement to produce such lists, which previously has been deemed not consistent with the risk-based approach adopted in CIP version 5/6 (because the development and accurate maintenance of such lists would consume large resources that would provide greater benefits to cyber security if applied elsewhere). At this time Seattle does not have alternative language to suggest to resolve this conundrum, which is inherent to the structure of CIP version 5/6. Perhaps a revision of the definition for Low impact Removable Media to reference only a temporary connection “to a BES Cyber System at a low impact facility” might work, but Seattle remains unconvinced that such a definition would prove auditable.

Ginette Lacasse, On Behalf of: Seattle City Light, WECC, Segments 1, 3, 4, 5, 6

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Ryan Olson, Portland General Electric Co., 5, 1/23/2017

- 0 - 0

The proposed definition of Removable Media (RM) implies additional requirements for entities to comply with that is in misalignment with standards that are currently approved and in effect. The purpose of CIP-003-7(i) is to create RM requirements for Low Impact BES Cyber Systems, yet none of the criteria of item 4 of the definition can be achieved for Lows without imposing additional, and improper, requirements upon the Registered Entities. Item 4 bullets 2 and 3 are omitted because they explicitly require the device or network to be associated with a high or medium impact, leaving just the direct connection to a BES Cyber Asset as the required #4 criteria. However, CIP-002-5.1 R1.3 reads “Identify each asset that contains a low impact BES Cyber System according…if any (a discrete list of low impact BES Cyber Systems is not required).” The requirement explicitly states that a discrete list of BES Cyber Systems is not required. BES Cyber Systems are defined as “One or more BES Cyber Assets logically grouped”, showing that BES Cyber Assets are a sub-componet of a BES Cyber System. CIP-002-5.1 explicitly states that a list of low impact BCS is not required, yet this definition of TCA would require entities to evaluate and inventory, and maintain that inventory, to identify every BES Cyber Asset in order to correctly identify RM that could be used at a low impact site. Entergy proposes some verbiage to include low impact BCS, while not adding additional inventorying requirements such as “Anticipated for use within a low impact BCS, if any”.

Julie Hall, Entergy, 6, 1/23/2017

- 0 - 0

Daniel Gacek, Exelon, 1, 1/23/2017

- 0 - 0

Aaron Cavanaugh, On Behalf of: Bonneville Power Administration, WECC, Segments 1, 3, 5, 6

- 0 - 0

Luminant, Segment(s) 6, 7, 5, 1/24/2017

- 0 - 0

Maryclaire Yatsko, On Behalf of: Seminole Electric Cooperative, Inc., FRCC, Segments 1, 3, 4, 5, 6

- 0 - 0

Request that the guidance be added to the Guidance and Technical Basis (GTB) on the need for the additional language referencing High and Medium Impact with regard to ESP’s and PCA’s to the Removable Media definition.  Guidance would show that low impact BES Cybers Systems may be configured in a way that would meet the definition of ESP even though an ESP is not required or been identified.

Colorado Springs Utilities, Segment(s) 5, 3, 1, 6, 5/6/2015

- 0 - 0

Jason Snodgrass, 1/24/2017

- 0 - 0

Duke Energy , Segment(s) 1, 5, 6, 4/10/2014

- 0 - 0

Illinois Municipal Electric Agency supports comments provided by the American Public Power Association.

Bob Thomas, 1/25/2017

- 0 - 0

Lan Nguyen, On Behalf of: CenterPoint Energy Houston Electric, LLC, Texas RE, Segments 1

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Aaron Austin, On Behalf of: AEP, SPP RE, RF, Segments 1, 3, 5, 6

- 0 - 0

Jeffrey DePriest, 1/25/2017

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

- 0 - 0

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

David Gordon, 1/25/2017

- 0 - 0

Since PCA is already defined by NERC, NRG recommends deleting associated with high or medium impact BES Cyber Systems since “associated” could be misunderstood and appears to be redundant.

Kara White, On Behalf of: NRG - NRG Energy, Inc., FRCC, MRO, WECC, Texas RE, NPCC, SERC, SPP RE, RF, Segments 3, 4, 5, 6

- 0 - 0

  1. Similar to TCAs, we suggest the SDT revise its approach and remove low impact BES Cyber Security requirements from the definition of Removable Media (RM).  We feel its relevance on controls required for high, medium, and low impact BES Cyber Systems is not the best way to address the directives listed in FERC Order No. 822.  The proposed revisions implicitly require low impact entities to have the same level of risk mitigiations in places as if they were associated with high and medium impact BES Cyber Systems.  We believe the SDT should avoid the inclusion of low impact BES Cyber Systems entirely or provide proof of a  risk analysis to substatntiate this activity.
  2. We suggest the SDT consider another method to address the FERC directive that still preserves the low impact requirements and the explicit exclusion from being required to have an inventory list of low impact assets.  Such an approach could include Removable Media in the technical guidance under Electronic Access Controls that are currently approved.
  3. One possible approach is for low impact entities to have a documented process that applies electronic access controls for Removable Media to low impact assets.
    1. Auditors could verify that the entity has developed the documented process, and the entity could demonstrate compliance by providing the document as evidence.
    2. This approach also preserves the disparate treatment of low and medium impact assets by assigning different requirement levels that commensurate with BES level risks

ACES Standards Collaborators, Segment(s) 1, 5, 3, 4, 1/25/2017

- 0 - 0

Mike Anctil, 1/25/2017

- 0 - 0

Tacoma Power supports comments submitted by APPA.

John Merrell, Tacoma Public Utilities (Tacoma, WA), 1, 1/25/2017

- 0 - 0

Add a « Low impact BES » item in the TCA definition. This will exempt the inventory requirement for low to demonstrate compliance for the TCA.

The proposed definition of Removable Media is:

Storage media that:

5. are not Cyber Assets,

6. are capable of transferring executable code,

7. can be used to store, copy, move, or access data, and

8. are directly connected for 30 consecutive calendar days or less to a:

BES Cyber Asset,

Low impact BES Cyber System,

network within an Electronic Security Perimeter (ESP) containing high or medium impact BES Cyber Systems, or

Protected Cyber Asset associated with high or medium impact BES Cyber Systems. 

Roger Dufresne, 1/25/2017

- 0 - 0

Melanie Seader, On Behalf of: Edison Electric Institute, NA - Not Applicable, Segments NA - Not Applicable

- 0 - 0

Suggest to dd a « Low impact BES » item in the TCA definition. This will exempt the inventory requirement for low to demonstrate compliance for the TCA.

The proposed definition of Removable Media is:

Storage media that:

  1. are not Cyber Assets,

  2. are capable of transferring executable code,

  3. can be used to store, copy, move, or access data, and

  4. are directly connected for 30 consecutive calendar days or less to a:

    • BES Cyber Asset,

    • Low impact BES Cyber System,

    • network within an Electronic Security Perimeter (ESP) containing high or medium impact BES Cyber Systems, or

    • Protected Cyber Asset associated with high or medium impact BES Cyber Systems.

Si Truc Phan, On Behalf of: Hydro-Qu?bec TransEnergie, NPCC, Segments 1

- 0 - 0

Wendy Center, U.S. Bureau of Reclamation, 5, 1/25/2017

- 0 - 0

Amy Casuscelli, On Behalf of: Xcel Energy, Inc. - MRO, WECC, SPP RE - Segments 1, 3, 5, 6

- 0 - 0

Santee Cooper agrees with APPA's comment/concern. 

Santee Cooper , Segment(s) 1, 5, 1/25/2017

- 0 - 0

Texas RE noticed the TCA definition includes examples of what directly connected means, “directly connected (e.g., using Ethernet, serial, Universal Serial Bus, or wireless including near field or Bluetooth communication) for 30 consecutive calendar days or less to a”.

 

There are no examples for “directly connected” listed in the Removable Media definition. Texas RE recommends that the SDT provide examples to provide clarity to the industry. There are instances when removable media may be physically directly connected but not active until mounted.

Rachel Coyne, Texas Reliability Entity, Inc., 10, 1/25/2017

- 0 - 0

Patricia Lynch, 1/25/2017

- 0 - 0

Patricia Lynch, 1/25/2017

- 0 - 0

Request that the guidance be added to the Guidance and Technical Basis (GTB) on the need for the additional language referencing High and Medium Impact with regard to ESP’s and PCA’s to the Removable Media definition.  Guidance would show that low impact BES Cybers Systems may be configured in a way that would meet the definition of ESP even though an ESP is not required or been identified.

FMPA, Segment(s) , 12/5/2016

- 0 - 0

SPP Standards Review Group, Segment(s) , 1/25/2017

- 0 - 0

Southern Company, Segment(s) 1, 3, 5, 6, 8/3/2016

- 0 - 0

RSC no Dominion and OPG, Segment(s) 1, 0, 2, 4, 5, 6, 7, 3, 1/20/2017

- 0 - 0

- 0 - 0

Sandra Shaffer, Berkshire Hathaway - PacifiCorp, 6, 1/25/2017

- 0 - 0

Request that the guidance be added to the Guidance and Technical Basis (GTB) on the need for the additional language referencing High and Medium Impact with regard to ESP’s and PCA’s to the Removable Media definition.  Guidance would show that low impact BES Cybers Systems may be configured in a way that would meet the definition of ESP even though an ESP is not required or been identified. The definition does not spell out what defines RMin a low impact environment.  Should the definition include additional instruction related to item 4 such as “connected to a cyber asset located in an asset contiaing low impact BES Cyber Systems”?

Ronald Donahey, TECO - Tampa Electric Co., 3, 1/25/2017

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Hot Answers

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Other Answers

Jamie Monette, Allete - Minnesota Power, Inc., 1, 1/9/2017

- 0 - 0

RoLynda Shumpert, On Behalf of: SCANA - South Carolina Electric and Gas Co., SERC, Segments 1, 3, 5, 6

- 0 - 0

Christopher Chavez, On Behalf of: Salt River Project, WECC, Segments 1, 3, 5, 6

- 0 - 0

The NSRF clearly understands that all entities regardless of size can be the door way for malicious code to entire into the BES systems.  This includes small entities with one Low Impact BES Cyber Systems only (read low risk) (maybe a generator, one Transmission sub station,  or control system).  With this is mind, the NSRF has the following concerns that the SDT should clarify for all entities with Low Impact BES Cyber Systems.

 

The NSRF has concerns with Attachment 1, part 5.2 for entities that have Low Impact BES Cyber Systems, only.  The actionable items in 5.2 is for us the entity to “Review” items that the “other party” needs to do to do prior to connecting to our Low Impact BES Cyber System.  Please clariy what “review” means?  What is acceptable within our review process?  Attachment 2 states examples of electronic mail, policies, contracts, etc.  Do we just review that the “other party” states that they will accomplish the attributes of 5.2 and have that stated within a contract, e-mail, STOW, etc.  and we are compliant?   This will play a role with proprietary software when a vendor will not provide associated evidence.

 

This clarity will reduce the compliance risks for the small entity and will assure that entities meet the attributes of 5.2, thus maintaining a secure BPS.

5.1 For Transient Cyber Asset(s) managed by the Responsible Entity, if any, the use of one or a combination of the following in an ongoing or on-demand manner (per Transient Cyber Asset capability):

• Antivirus software, including manual or managed updates of signatures or patterns;

• Application whitelisting; or

• Other method(s) to mitigate the introduction of malicious code.

 

Please clarify how the SDT wishes to use the semicolon within the first bullet of 5.1?  Does this mean “and” or “or” as in the second bullet?  We have the same question for all semicolons in 5.2 as well.  The NSRF believes by adding a simple “or” after each semicolon, we will clearly know what the intent of the bulleted items are.

MRO NSRF, Segment(s) 3, 4, 5, 6, 1, 2, 1/4/2017

- 1 - 0

Bobby Olsen, Salt River Project, 6, 1/19/2017

- 0 - 0

Dennis Minton, On Behalf of: Dennis Minton, , Segments 1, 3

- 0 - 0

We continue to have concerns about how the GTB are factored into Compliance and Enforcement.  In some cases it appears that they create “requirements” that must be incorporated into your program; this is inconsistent with prior FERC precedent.  On the other hand, it is not clear whether or not you can rely on the GTB in developing your program and ensuring compliance. This concern continues to fail to be addressed by the SDT. With respect to Attachment 1 Section 3, and Attachment 2, Section 3.1, it doesn't make sense to keep referring to physical location when it comes to electronic controls (as previously noted).   

Sarah Gasienica, 1/19/2017

- 0 - 0

- 0 - 0

The language is open ended and fails to provide discrete direction to entities on how to implement a plan.  This will lead to subjective enforcement, with the possibility for significant discrepancies and differences between regions.

Michael Ward, 1/20/2017

- 0 - 0

Tennessee Valley Authority, Segment(s) 1, 3, 5, 6, 9/1/2016

- 0 - 0

Sean Bodkin, Dominion - Dominion Resources, Inc., 6, 1/23/2017

- 0 - 0

Seattle City Light agrees with the revisions so far as they go, but finds that they do not address the question of what would be acceptable evidence of the existence of any Low impact Transient Cyber Asset (based on the proposed definition) in the absence of an explicit list of Low impact BES Cyber Systems and Assets at a facility. As discussed in the definition comment above, Seattle does not have a solution to the problem, which is inherent to the structure of CIP verion 5/6.

Ginette Lacasse, On Behalf of: Seattle City Light, WECC, Segments 1, 3, 4, 5, 6

- 0 - 0

Yes

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Ryan Olson, Portland General Electric Co., 5, 1/23/2017

- 0 - 0

Agree with CIP-003-7(i), Attachment 1, Section 5 as written in this draft. As written, this verbiage implies entities has latitude to implement a strategy based on a risk to achieve the goal of the standard. See response to question 4 below for concerns regarding actual implementation of plans.

Julie Hall, Entergy, 6, 1/23/2017

- 1 - 0

Exelon supports the changes made to CIP-003-7(i), R2, Attachment 1, adding Section 5; however, we request the SDT consider the following adjustments:

  1. The language in Attachment 1, Section 5, regarding “achieve the objective of mitigating the risk of the introduction of malicious code,”  differs from the language in CIP-010-2, R4, Attachment 1, Section 1.3, which states “…achieves the objective of mitigating the introduction of…”  Exelon requests the SDT consider aligning the two obligations to the language found in CIP-010-2, R4 or add clarification to the Guidelines and Technical Basis that provides clarity regarding the addition of “...the risk of…” and whether there are any additional or different expectations for Responsible Entities related to CIP-003-7(i), R2.    Exelon is concerned that the addition of “risk” could be interpreted to require performing and documenting a risk assessment of all of the risks posed by the introduction of malicious code.    

The following sentence (or something comparative) could be added to the Guidelines and Technical Basis as the last sentence in the first paragraph related to Section 5.1 if the SDT determines the requirement language does not require alignment:  “When determining the method(s) to mitigate the introduction of malicious code, it is not intended Responsible Entities have to perform and document a risk assessment to determine all of the risks associated with the introduction of malicious code.”    

  1. Attachment 1, Section 5.3.2 states, “Mitigation of the threat of detected malicious code on the Removable Media prior to connecting Removable Media to a low impact BES Cyber System.”  Exelon proposes a one-word change to replace the “…threat of…” to “…threat from…”    This minor wording change helps to clarify the meaning of the obligation.  Using the word “from” makes it clear that the mitigation of the threat is associated with already detected malicious code, as opposed to mitigation of a general threat of malicious code that may occur in the future.

Daniel Gacek, Exelon, 1, 1/23/2017

- 0 - 1

Aaron Cavanaugh, On Behalf of: Bonneville Power Administration, WECC, Segments 1, 3, 5, 6

- 0 - 0

Luminant, Segment(s) 6, 7, 5, 1/24/2017

- 0 - 0

This is a low impact requirement rather than a high or medium impact requirement.  While risks of malicious code are definitely present, the reduced risk level would make this entire requirement more effective by requiring the entity document and implement a security program with appropriate controls that prevent introduction of malicious code.  Examples of appropriate controls are: application whitelisting, antivirus, use of bootable CDs without known malware, contracts with vendors, etc.  Note that use of third party TCA is expected to be much more frequent on low impact BCS and highly presecriptive requirements are less effective.

 

Should the above approach not be acceptable, requirement 5.3.1 and 5.3.2 should be consolidated into a single statement.  A requirement to scan prior to connecting and then separately document and mitigate is redundant. The Removable media simply needs to be clean prior to connecting to a Transient Cyber Asset.  Seminole suggests making that the requirement.

 For example, the language could be modified to state:

 For Removable Media, document and implement methods that prevent the introduction of malicious code on BES Cyber Assets when connecting Removable Media.  In cases of detected malicious code that cannot be removed, the entity shall document how the identified malware is mitigated.

Maryclaire Yatsko, On Behalf of: Seminole Electric Cooperative, Inc., FRCC, Segments 1, 3, 4, 5, 6

- 0 - 0

 1) The bulleted list creates requirements that are too prescriptive.  Use alternative language for Section 5.1 and 5.2 to remove the bullet points (because they may be used against you in some fashion in the future), and re-write the requirements.  The bullet points should go into the GTB section so that there is less chance for a misinterpretation of reinterpretation that would require the implementation of more than one of the bulleted point  inorder to meet compliance.

2) As written, the requirements listed for TCAs in CIP-003-7(i) for Low Impact assets is a subset of the requirements for high and medium impact included in CIP-010-2 R4.  As is or if changed the GTB section should include a statement the low impact requirements are a subset of those for High and Medium.

Colorado Springs Utilities, Segment(s) 5, 3, 1, 6, 5/6/2015

- 0 - 0

Comments: Both sections 5.1 and 5.2 contain an option of “Other method(s) to mitigate the introduction of malicious code” which grants responsible entities flexibility in choosing alternative methods not included in the list of bulleted items as long as the methods achieve the core security objective outlined in section 5.  Therefore, it seems that emphasis is placed on achieving the security objective established by the core of section 5 and the distinction between 5.1 and 5.2 is for the plan to include and cover whom is managing TCAs and not specificly to capture the various options bulleted within the required plan. 

As such, GTC believes the bullet point “options” introduces unneccesary prescriptive language and can be removed from the requirements without changing the intent of the requirement whatsoever and the drafting team could simplify with and affirmative ballot.  GTC recognizes these options provide contextual ideas of how one could go about achieving the objective of mitigating the risk of the introduction of malicious code to low impact BES Cyber Systems and further recommends that they be relocated into the guidelines and technical basis of the standard. 

This streamlined revision to section 5 could be simplified for clarity of implementation on the front end and clarity of compliance testing on the audit end as follows:

Transient Cyber Asset and Removable Media Malicious Code Risk Mitigation: Each Responsible Entity shall implement, except under CIP Exceptional Circumstances, one or more plan(s) to achieve the objective of mitigating the risk of the introduction of malicious code to low impact BES Cyber Systems through the use of Transient Cyber Assets or Removable Media. The plan(s) shall include:

5.1 Method(s) to mitigate the introduction of malicious code for Transient Cyber Asset(s) managed by the Responsible Entity, if any.

5.2 Method(s) to mitigate the introduction of malicious code for Transient Cyber Asset(s) managed by a party other than the Responsible Entity, if any.

5.3 For Removable Media, the use of each of the following:

5.3.1 Method(s) to detect malicious code on Removable Media using a Cyber Asset other than a BES Cyber System; and

5.3.2 Mitigation of the threat of detected malicious code on the Removable Media prior to connecting Removable Media to a low impact BES Cyber System.

Jason Snodgrass, 1/24/2017

- 0 - 0

Duke Energy would like to see added clarification within the Guidelines and Technical Basis around the concept of an acceptable review of a 3rd party vendors malware mitigation mechanisms. Currently, in Section 5.2 of Attachment 1, a Responsible Entity is required to “Review” one or a combination of the malware mitigation mechanisms of a 3rd party vendor. Our concern is that it is unclear what constitutes an acceptable “review” of these mechanisms. It is possible that what is considered an acceptable review by one entity, may not be considered acceptable by another. We suggest the drafting team consider adding language to the Guidelines and Technical Basis further describing what constitutes an acceptable review.

Duke Energy , Segment(s) 1, 5, 6, 4/10/2014

- 0 - 0

Illinois Municipal Electric Agency supports comments provided by the American Public Power Association.

Bob Thomas, 1/25/2017

- 0 - 0

Lan Nguyen, On Behalf of: CenterPoint Energy Houston Electric, LLC, Texas RE, Segments 1

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

We like to see examples how to have the ability to restrict malware to the TCA's. Also like to see some examples around technical guidance and mitigation plans. Possibly adding administrative control methods in the technical basis sections for transient devices. Add language in the technical basis restricting movement of TCA's.

Aaron Austin, On Behalf of: AEP, SPP RE, RF, Segments 1, 3, 5, 6

- 0 - 0

Jeffrey DePriest, 1/25/2017

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

- 0 - 0

ITC Holdings agrees with the comment submitted by NSRF – see below:


The NSRF clearly understands that all entities regardless of size can be the door way for malicious code to entire into the BES systems.  This includes small entities with one Low Impact BES Cyber Systems only (read low risk) (maybe a generator, one Transmission sub station,  or control system).  With this is mind, the NSRF has the following concerns that the SDT should clarify for all entities with Low Impact BES Cyber Systems.
 

The NSRF has concerns with Attachment 1, part 5.2 for entities that have Low Impact BES Cyber Systems, only.  The actionable items in 5.2 is for us the entity to “Review” items that the “other party” needs to do to do prior to connecting to our Low Impact BES Cyber System.  Please clariy what “review” means?  What is acceptable within our review process?  Attachment 2 states examples of electronic mail, policies, contracts, etc.  Do we just review that the “other party” states that they will accomplish the attributes of 5.2 and have that stated within a contract, e-mail, STOW, etc.  and we are compliant?   This will play a role with proprietary software when a vendor will not provide associated evidence.
 

This clarity will reduce the compliance risks (burden) for the small entity and will assure that entities meet the attributes of 5.2. 

5.1 For Transient Cyber Asset(s) managed by the Responsible Entity, if any, the use of one or a combination of the following in an ongoing or on-demand manner (per Transient Cyber Asset capability):

• Antivirus software, including manual or managed updates of signatures or patterns;

• Application whitelisting; or

• Other method(s) to mitigate the introduction of malicious code.

Please clarify how the SDT wishes to use the semicolon within the first bullet of 5.1?  Does this mean “and” or “or” as in the second bullet?  We have the same question for all semicolons in 5.2 as well.  The NSRF believes by adding a simple “or” after each semicolon, we will clearly know what the intent of the bulleted items are.

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

MMWEC supports the comments submitted by Georgia Transmission Corp. regarding streamling Section 5 by moving the bullets to GTB and keeping the security objective in the Attachment.

 

David Gordon, 1/25/2017

- 0 - 0

Kara White, On Behalf of: NRG - NRG Energy, Inc., FRCC, MRO, WECC, Texas RE, NPCC, SERC, SPP RE, RF, Segments 3, 4, 5, 6

- 0 - 0

  1. We have concerns with part 5.2 of Attachment 1 for applicable entities that only have Low Impact BES Cyber Systems.  Many of these entities provide a small risk to the BES since they only have one low impact BES Cyber Systems (e.g. a generator, one Transmission substation, or a single control system).  Will Regional Entities conduct the same audit for small entities as they would for large multi-regional corporate companies? What is the impact when a vendor does not comply with the request listed in part 5.2?
  2. We also question the need for additional explicit requirements to validate vendor security and patch management plans as part of a low impact entity’s cyber security policies.  We believe these requirements are already incorporated in an entity’s Electronic Access Controls Policy. These additional requirements are a burden to existing low impact entities that may only have one or two TCA-applicable or RM-applicable BES cyber assets. We recommend removing these requirements for low Impact entities until after the effective date for NERC Reliability Standard CIP-007-3 (i.e. September 1, 2018).
  3. The inclusion of TCA and RM with the final definition of LERC is unnecessary. We don't agree with the SDT's approach of posting two options, and then recommend the all-inclusive option over the other.  The SDT should wait for industry to provide feedback on both options or post only one path forward and determine if industry supports it. The one option adds additional risk for ballot approval.

ACES Standards Collaborators, Segment(s) 1, 5, 3, 4, 1/25/2017

- 0 - 0

This NERC project is adding a new Section 5 bringing into scope Transient Cyber Assets and Removable Media for Low Impact Facilities which is a much larger scope than our High and Medium Impact Program without any extension of time for compliance indicated for implementation. This will be impactful to the Power System.

Mike Anctil, 1/25/2017

- 0 - 0

Tacoma Power supports comments submitted by APPA.

In Attachment 1, Section 5, 5.2, what frequency is intended by the words "prior to"?  Is this intended to be once upon execution of a vendor/contractor support contract, or is it intended to be at some other interval/frequency?

John Merrell, Tacoma Public Utilities (Tacoma, WA), 1, 1/25/2017

- 0 - 0

Summary of changes in page 44 of the guidelines CIP010 mentioned :

“All requirements related to TCA and RM are included within a single standard, CIP010. But requirements exist also in CIP-003-07 R2 . HQP suggest to modify the summary of changes.

The word “Managed” should be in lower case for paragraph in the page 56 of 62 “Requirement R2, Attachment 1, Section 5.1 - Transient Cyber Asset(s) Managed by the Responsible Entity”.

It could be usefull to introduce base of risk in the case of a TCA connected to LOW impact BES systems without external connectivity.

Roger Dufresne, 1/25/2017

- 0 - 0

Melanie Seader, On Behalf of: Edison Electric Institute, NA - Not Applicable, Segments NA - Not Applicable

- 0 - 0

Summary of changes in page 44 of the guidelines CIP010 mentioned :

“All requirements related to TCA and RM are included within a single standard, CIP010. But requirements exist also in CIP-003-07 R2 . HQP suggest to modify the summary of changes.

The word “Managed” should be in lower case for paragraph in the page 56 of 62 “Requirement R2, Attachment 1, Section 5.1 - Transient Cyber Asset(s) Managed by the Responsible Entity”.

 

It could be usefull to introduce base of risk in the case of a TCA connected to LOW impact BES systems without external connectivity.

Si Truc Phan, On Behalf of: Hydro-Qu?bec TransEnergie, NPCC, Segments 1

- 0 - 0

Reclamation appreciates the Standards Drafting Team's consideration of prior recommendations. Reclamation agrees with the changes and has the following question:

 

In this version of CIP-003-7(i), did the SDT intend to add guidance regarding the new section on page 9 under Requirement 1 "1.2.6 Declaring and responding to CIP Exceptional Circumstances" in Attachment 1 and/or Attachment 2?

Wendy Center, U.S. Bureau of Reclamation, 5, 1/25/2017

- 0 - 0

Amy Casuscelli, On Behalf of: Xcel Energy, Inc. - MRO, WECC, SPP RE - Segments 1, 3, 5, 6

- 0 - 0

Santee Cooper agrees with APPA's comments. 

Santee Cooper , Segment(s) 1, 5, 1/25/2017

- 0 - 0

Texas RE’s appreciates the SDT’s efforts to implement the FERC directive in Order No. 822 to “develop modifications to the CIP Reliability Standards to provide mandatory protection for transient devices used at Low Impact BES Cyber Systems based on the risk posed to the bulk electric system reliability.”  In implementing this directive, Texas RE notes that the SDT appears to have used the existing Transient Cyber Asset (TCA) and Removable Media requirements for medium and high impact BES Cyber Systems and associated Protected Cyber Assets set forth in CIP-10-2, Attachment 1, Sections 1 through 3 as the basis for developing the new TCA and removable media requirements for low impact BES Cyber Systems. 

 

While Texas RE agrees with this general approach, Texas RE notes that the SDT elected to not include all applicable requirements.  For instance, the current draft of CIP-003, Attachment 1, Section 5 omits any requirements to mitigate software vulnerabilities (CIP-10-2, Attachment 1, Section 1.3 for TCAs managed by the Responsible Entity; CIP-10-2, Attachment 1, Section 2.1 for TCAs managed by a party other than the Responsible Entity).  Texas RE requests that the SDT provide its risk-based justification for why those aspects of the CIP-010-2, Attachment 1 requirements for medium and high impact TCAs and removable media are not correspondingly extended to similar low impact devices.  Among other things, this will assist Texas RE in its efforts to understand, evaluate, and ensure compliance with the new low impact requirements. 

 

 

In addition, Texas RE noticed the following:

  • There is no distinction provided for Removable Media used by different parties.  Was that the intent of the SDT?  As written it appears to be for any Removable Media used by any party (e.g., vendor, or third party technician/personnel).

     

  • Texas RE recommends that the SDT specifically address the impact of backup tapes, libraries, and drives. More specifically Texas RE recommends addressing magnetic tapes, in regard to section 5.3.2. How would an entity mitigate the threat of detected malicious code on magnetic tapes prior to connecting it to a high, medium, or low impact BES Cyber System?

     

  • On Page 29, Section 5 - Transient Cyber Asset and Removable Media Malicious Code Risk Mitigation; there is an extra “_” that is not needed after the colon symbol.

Rachel Coyne, Texas Reliability Entity, Inc., 10, 1/25/2017

- 0 - 0

Patricia Lynch, 1/25/2017

- 0 - 0

Patricia Lynch, 1/25/2017

- 0 - 0

1) The bulleted list creates requirements that are too prescriptive.  Use alternative language for Section 5.1 and 5.2 to remove the bullet points (because they may be used against you in some fashion in the future), and re-write the requirements.  The bullet points should go into the GTB section so that there is less chance for a misinterpretation of reinterpretation that would require the implementation of more than one of the bulleted point  inorder to meet compliance.

 

2) As written, the requirements listed for TCAs in CIP-003-7(i) for Low Impact assets is a subset of the requirements for high and medium impact included in CIP-010-2 R4.  As is or if changed the GTB section should include a statement the low impact requirements are a subset of those for High and Medium.

FMPA, Segment(s) , 12/5/2016

- 0 - 0

SPP Standards Review Group, Segment(s) , 1/25/2017

- 0 - 0

Southern Company, Segment(s) 1, 3, 5, 6, 8/3/2016

- 0 - 0

RSC no Dominion and OPG, Segment(s) 1, 0, 2, 4, 5, 6, 7, 3, 1/20/2017

- 0 - 0

- 0 - 0

Sandra Shaffer, Berkshire Hathaway - PacifiCorp, 6, 1/25/2017

- 0 - 0

 Recommend revisions to remove the bulleted list and re-write the requirements.  The bullet points should go into the GTB section so that there is less chance for a misinterpretation that would require the implementation of more than one of the bulleted point  in order to meet compliance.

 

Ronald Donahey, TECO - Tampa Electric Co., 3, 1/25/2017

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Hot Answers

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Other Answers

Jamie Monette, Allete - Minnesota Power, Inc., 1, 1/9/2017

- 0 - 0

RoLynda Shumpert, On Behalf of: SCANA - South Carolina Electric and Gas Co., SERC, Segments 1, 3, 5, 6

- 0 - 0

Christopher Chavez, On Behalf of: Salt River Project, WECC, Segments 1, 3, 5, 6

- 0 - 0

Please see question 3 for comments concerning “review”.  By explaining what the acceptable level of “review” is, the small entity will not be caught in a catch 22.  Whereby the “other party” will not state that they meet the attributes of 5.2 and the small entity will have a Low Impact BES Cyber System that cannot be upgraded.   

MRO NSRF, Segment(s) 3, 4, 5, 6, 1, 2, 1/4/2017

- 0 - 0

Bobby Olsen, Salt River Project, 6, 1/19/2017

- 0 - 0

Dennis Minton, On Behalf of: Dennis Minton, , Segments 1, 3

- 0 - 0

We continue to have concerns about how the GTB are factored into Compliance and Enforcement.  In some cases it appears that they create “requirements” that must be incorporated into your program; this is inconsistent with prior FERC precedent.  On the other hand, it is not clear whether or not you can rely on the GTB in developing your program and ensuring compliance. This concern continues to fail to be addressed by the SDT. With respect to Attachment 1 Section 3, and Attachment 2, Section 3.1, it doesn't make sense to keep referring to physical location when it comes to electronic controls (as previously noted).   

Sarah Gasienica, 1/19/2017

- 0 - 0

- 0 - 0

Same as previous answer.

Michael Ward, 1/20/2017

- 0 - 0

Tennessee Valley Authority, Segment(s) 1, 3, 5, 6, 9/1/2016

- 0 - 0

Sean Bodkin, Dominion - Dominion Resources, Inc., 6, 1/23/2017

- 0 - 0

Seattle City Light agrees with the revisions so far as they go, but finds that they do not address the question of what would be acceptable evidence of the existence of any Low impact Removable Media Asset (based on the proposed definition) in the absence of an explicit list of Low impact BES Cyber Systems and Assets at a facility. As discussed in the definition comment above, Seattle does not have a solution to the problem, which is inherent to the structure of CIP verion 5/6.

Ginette Lacasse, On Behalf of: Seattle City Light, WECC, Segments 1, 3, 4, 5, 6

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Ryan Olson, Portland General Electric Co., 5, 1/23/2017

- 0 - 0

CIP-003-7(i), Attachment 2, Section 5, Part 3 is inconsistent with Part 1. Part 3 states that “Examples of evidence for Section 5.3.1 may include, but are not limited to, documented process(es) of the method(s) used to detect malicious code such as results of scan settings for Removable Media”. Entergy views the documented process(es) and the results of scanning as two separate pieces of evidence. Part 1 identifies the documented process(es) as an acceptable form of evidence with no requirement for scan results for TCA. Part 3 as written implies that all scans results of applicable Removable Media must be maintained in order to provide proper evidence of compliance with CIP-003-7(i), Attachment 1, Section 5.3. This is in stark contrast to the proposed “Supplemental Material” which states that “the SDT does not intend for a Responsible Entity to conduct a review for every single connection of that Removable Media, but implement their process(es) in manner that protects all BES Cyber Systems where the Removable Media may be used. The intent is also not to require a log documenting each connection of Removable Media to a BES Cyber Asset.” Entergy proposes that CIP-003-7(i), Attachment 2, Section 5, Part 3 be rewritten to more closely mirror Part 1 which identifies the documented process as the evidence item. Specific scan results should be identified as potential additional evidence to support Registered Entities programs.

Julie Hall, Entergy, 6, 1/23/2017

- 0 - 0

Daniel Gacek, Exelon, 1, 1/23/2017

- 0 - 0

Aaron Cavanaugh, On Behalf of: Bonneville Power Administration, WECC, Segments 1, 3, 5, 6

- 0 - 0

We recommend modifying the first sentence of 5.3.1 to read: “Examples of evidence for Section 5.3.1 may include, but are not limited to, documented process(es) of the method(s) used to detect malicious code, including an example of the results.” The original language is confusing, and we believe we should avoid the suggestion of a requirement to capture and retain transactional-level evidence as this would be administratively burdensome.

Luminant, Segment(s) 6, 7, 5, 1/24/2017

- 0 - 0

Considering the current draft language of the standard, the required evidence can be improved.  There is a tradeoff that must be considered between adequate evidence to demonstrate both 1) compliance and assurance that the risk of introduction of malware is mitigated and 2) evidence collection across a large number of sites becoming excessively burdensome.  The standard and evidence must be both effective and efficient.

The expectations for adequate evidence do not fit the audit style currently being used in compliance monitoring.  For example, the CIP Version 5 Evidence Request is clearly written to require often extensive documentation of implementation, whereas the measures documented are inconsistent.  The measures should be built to provide an example of evidence that would either meet the current evidence request approach or to clearly communicate the intent of the SDT what appropriate evidence would be. 

 For Measure 5.1, an example of alternative language to clarify audit expectations would be:

Examples of evidence for Section 5.1 may include, but are not limited to,

  1. Documentation of the method(s) used to mitigate the introduction of malicious code such as antivirus software and processes for managing signature or pattern updates, application whitelisting practices, processes to restrict communication, or other method(s) to mitigate the introduction of malicious code; and

  2. Either documentation of an appropriate set of controls that provide a high level of assurance that malware is not present on the Transient Cyber Asset prior to use; or documentation that the Transient Cyber Asset followed the documented method and demonstrates that no identifiable malware is present prior to use.

If a Transient Cyber Asset does not have the capability to use method(s) that mitigate the introduction of malicious code, evidence may include documentation by the vendor or Responsible Entity that identifies that the Transient Cyber Asset does not have the capability.

For Measure 5.3, an example of alternative language that may meet this intent could include:

Examples of evidence for Section 5.3 may include, but are not limited to,

  1. Documented process(es) of the method(s) used to detect malicious code; and

  2. Either documentation of an appropriate set of controls that provide a high level of assurance that malware is not present on the Removable Media prior to use; or documentation that the Transient Cyber Asset followed the documented method and demonstrates that no identifiable malware is present prior to use.

Maryclaire Yatsko, On Behalf of: Seminole Electric Cooperative, Inc., FRCC, Segments 1, 3, 4, 5, 6

- 0 - 0

The complexity of the  sentences are difficult to read and understand.  Suggest revising to bulleted lists.    The evidence requirements seem to require an inventory of TCA’s and RM.  This could be an issue in the same way that a list of BES Cyber Systems has been determined to be an issue.

Colorado Springs Utilities, Segment(s) 5, 3, 1, 6, 5/6/2015

- 0 - 0

Jason Snodgrass, 1/24/2017

- 0 - 0

Duke Energy , Segment(s) 1, 5, 6, 4/10/2014

- 0 - 0

Illinois Municipal Electric Agency supports comments provided by the American Public Power Association.

Bob Thomas, 1/25/2017

- 0 - 0

Lan Nguyen, On Behalf of: CenterPoint Energy Houston Electric, LLC, Texas RE, Segments 1

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Aaron Austin, On Behalf of: AEP, SPP RE, RF, Segments 1, 3, 5, 6

- 0 - 0

Jeffrey DePriest, 1/25/2017

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

- 0 - 0

ITC Holdings agrees with the comment submitted by NSRF – see below:


Please see question 3 for comments concerning “review”.  By explaining what the acceptable level of “review” is, the small entity will not be caught in a catch 22.  Whereby the “other party” will not state that they meet the attributes of 5.2 and the small entity will have a Low Impact BES Cyber System that cannot be upgraded.  

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

David Gordon, 1/25/2017

- 0 - 0

This change creates additional requirements for Low Impact BCS relating to change control (additional cost implications from an administrative standpoint with limited reliability benefit) (i.e. capture every time a TCA is connected to a system and this infers that an entity is required to document a discrete list of Cyber Assets for Low Impact BCS)

NRG recommends deleting the quoted portion of the phrase from Section 5 of Attachment 2, number 2:  Examples of evidence for Section 5.2 may include, but are not limited to, documentation from change management systems, electronic mail or procedures “that document a review of the installed antivirus update level” because it imposes change management requirements where there are not existing NERC requirements

Kara White, On Behalf of: NRG - NRG Energy, Inc., FRCC, MRO, WECC, Texas RE, NPCC, SERC, SPP RE, RF, Segments 3, 4, 5, 6

- 0 - 0

We disagree with the proposed language, as the SDT has only restated the content of the requirement language.   There is no process or guidance for an entity to follow when a vendor fails to comply with required request.  Is a vendor’s attestation sufficent proof for an entity to demonstrate reasonable assurance for compliance?  If so, an attestation should be included in the list of acceptable evidence for this requirement, and reflected in Attachment 2 to ensure consistent regional application. 

ACES Standards Collaborators, Segment(s) 1, 5, 3, 4, 1/25/2017

- 0 - 0

Mike Anctil, 1/25/2017

- 0 - 0

Tacoma Power supports comments submitted by APPA.

Does the Standards Drafting Team intend that any kind of sign-in sheets may be required at assets containing low impact BES Cyber Systems?

John Merrell, Tacoma Public Utilities (Tacoma, WA), 1, 1/25/2017

- 0 - 0

Section 5.1 in page 32 to 62: To lighten a obligation of maintaining an inventory of TCA of Low impact BES Cyber System, HQP suggest to remove the notion of Trancient asset capability and change the paragraph by “ the Responsible Entity or the vendor may document the method used to mitigate the introduction of malicious code” 

Roger Dufresne, 1/25/2017

- 0 - 0

Melanie Seader, On Behalf of: Edison Electric Institute, NA - Not Applicable, Segments NA - Not Applicable

- 0 - 0

Section 5.1 in page 32 to 62: To lighten a obligation of maintaining an inventory of TCA of Low impact BES Cyber System, HQP suggest to remove the notion of Trancient asset capability and change the paragraph by “ the Responsible Entity or the vendor may document the method used to mitigate the introduction of malicious code”

Si Truc Phan, On Behalf of: Hydro-Qu?bec TransEnergie, NPCC, Segments 1

- 0 - 0

Reclamation appreciates the Standards Drafting Team's consideration of prior recommendations. Reclamation agrees with the changes and has the following question:

 

In this version of CIP-003-7(i), did the SDT intend to add guidance regarding the new section on page 9 under Requirement 1 "1.2.6 Declaring and responding to CIP Exceptional Circumstances" in Attachment 1 and/or Attachment 2?

Wendy Center, U.S. Bureau of Reclamation, 5, 1/25/2017

- 0 - 0

Amy Casuscelli, On Behalf of: Xcel Energy, Inc. - MRO, WECC, SPP RE - Segments 1, 3, 5, 6

- 0 - 0

There is a concern with the requirement that not only requires an inventory of Transient Cyber Assets and Removable Media but it also requires evidence of chain of custody.  The SDT needs to provide clarity on what is required for "evidence of chain of custody".

Santee Cooper , Segment(s) 1, 5, 1/25/2017

- 0 - 0

Texas RE noticed the following:

  • Page 31, Section 1. Cyber Security Awareness; there is an extra “_” that is not needed after the colon symbol.

     

  • Page 31, Section 2. Physical Security Controls; there is an extra “_” that is not needed after the colon symbol.

     

  • Page 33, Section 5. Transient Cyber Asset and Removable Media Malicious Code Risk Mitigation; there no period ”.” at the end of the first continued paragraph.

Rachel Coyne, Texas Reliability Entity, Inc., 10, 1/25/2017

- 0 - 0

Patricia Lynch, 1/25/2017

- 0 - 0

Patricia Lynch, 1/25/2017

- 0 - 0

The complexity of the  sentences are difficult to read and understand.  Suggest revising to bulleted lists.    The evidence requirements seem to require an inventory of TCA’s and RM.  This could be an issue in the same way that a list of BES Cyber Systems has been determined to be an issue.

FMPA, Segment(s) , 12/5/2016

- 0 - 0

SPP Standards Review Group, Segment(s) , 1/25/2017

- 0 - 0

Southern Company, Segment(s) 1, 3, 5, 6, 8/3/2016

- 0 - 0

RSC no Dominion and OPG, Segment(s) 1, 0, 2, 4, 5, 6, 7, 3, 1/20/2017

- 0 - 0

- 0 - 0

Sandra Shaffer, Berkshire Hathaway - PacifiCorp, 6, 1/25/2017

- 0 - 0

Ronald Donahey, TECO - Tampa Electric Co., 3, 1/25/2017

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Hot Answers

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Other Answers

The approach of defining a plan allows the Responsible Entity to document processes that are supportable within its organization and in alignment with its change management processes. To avoid confusion with CIP-010 R1 requirements, we suggest the removal of "change management process" in the prior sentence.

 

Jamie Monette, Allete - Minnesota Power, Inc., 1, 1/9/2017

- 0 - 0

RoLynda Shumpert, On Behalf of: SCANA - South Carolina Electric and Gas Co., SERC, Segments 1, 3, 5, 6

- 0 - 0

Christopher Chavez, On Behalf of: Salt River Project, WECC, Segments 1, 3, 5, 6

- 0 - 0

MRO NSRF, Segment(s) 3, 4, 5, 6, 1, 2, 1/4/2017

- 0 - 0

Bobby Olsen, Salt River Project, 6, 1/19/2017

- 0 - 0

Dennis Minton, On Behalf of: Dennis Minton, , Segments 1, 3

- 0 - 0

We continue to have concerns about how the GTB are factored into Compliance and Enforcement.  In some cases it appears that they create “requirements” that must be incorporated into your program; this is inconsistent with prior FERC precedent.  On the other hand, it is not clear whether or not you can rely on the GTB in developing your program and ensuring compliance. This concern continues to fail to be addressed by the SDT. With respect to Attachment 1 Section 3, and Attachment 2, Section 3.1, it doesn't make sense to keep referring to physical location when it comes to electronic controls (as previously noted).   

Sarah Gasienica, 1/19/2017

- 0 - 0

- 0 - 0

Same as previous answer

Michael Ward, 1/20/2017

- 0 - 0

Tennessee Valley Authority, Segment(s) 1, 3, 5, 6, 9/1/2016

- 0 - 0

Sean Bodkin, Dominion - Dominion Resources, Inc., 6, 1/23/2017

- 0 - 0

Seattle City Light appreciates the extra efforts of the Standard Drafting Team to provide such guidance and technical information. However, Seattle asks that Guidelines and Technical Basis information be provided for new Section 1.2.6 as well. This guidance would address how a CIP Exceptional Circumstance is considered when applied against a requirement that does not explicitly mention that a CIP Expection Circumstance applies.

Ginette Lacasse, On Behalf of: Seattle City Light, WECC, Segments 1, 3, 4, 5, 6

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Ryan Olson, Portland General Electric Co., 5, 1/23/2017

- 0 - 0

Supplemental Material, Requirement R2, Attachment 1, Section 5.1 – Transient Cyber Asset(s) Managed by the Responsible Entity, Paragraph 4 states that if a device will be used to “For example, if the device is managed in an on-demand manner, but will be used to perform maintenance on several BES Cyber Asset(s), the Responsible Entity may choose to document that the Transient Cyber Asset has been updated before being connected as a Transient Cyber Asset for the first use of that maintenance work. The intent is not to require a log documenting each connection of a Transient Cyber Asset to a BES Cyber Asset.” This may imply that at least some logs might need to be created for connections of TCA to BCA, which is not a requirement stated in the standard for TCAs at low impact BCS, or even for TCAs at Highs and Mediums under CIP-010-2. Additionally, requiring documentation that a TCA was updated before connecting to a BCA removes the device from the on-going program and puts it into on-demand space due to “has been updated before being connected” implying the device is as up to date as possible, even though the on-going process may allow for devices to be updated on a longer regular interval. If the TCA was truly maintained as part of the entitiy’s on-going program, no additional log or documentation should be required as the device would be compliant with the standard as written.

Supplemental Material, Requirement R2, Attachment 1, Section 5.1 – Transient Cyber Asset(s) Managed by the Responsible Entity, Paragraph 4Mitigation of the threat of detected malicious code on the Removable

Media prior to connecting Removable Media to a low impact BES Cyber System.

Julie Hall, Entergy, 6, 1/23/2017

- 0 - 0

Daniel Gacek, Exelon, 1, 1/23/2017

- 0 - 0

BPA believes that for Transient Cyber Assets and Removable Media that are connected to both low impact and medium/high impact BES Cyber Systems--entities must manage these assets under the program that matches the highest impact level to which they will connect.

Aaron Cavanaugh, On Behalf of: Bonneville Power Administration, WECC, Segments 1, 3, 5, 6

- 0 - 0

Luminant, Segment(s) 6, 7, 5, 1/24/2017

- 0 - 0

Considering the current draft language of the standard, the GTB addresses the required points.  However, the messages are not clearly, simply, and constructively communicated.  While the teams have clearly put a considerable amount of work into ensuring each detail is correct, the overall message in the guidance gets lost. This results in opportunities for multiple different interpretations by various entities and auditors. 

One possible control is testing the operation of antivirus  to test signatures.  These should be specifically noted that use of test signatures is not considered identified malware. 

Section 5.2 (and likely all of the guidance) could be improved if the GTB approach was changed to treat malware protection as a program with specific objectives and a selection of example techniques that may be used to meet these objectives.  Further, the guidance should be coordinated with the requirements in development by the Supply Chain SDT.

Maryclaire Yatsko, On Behalf of: Seminole Electric Cooperative, Inc., FRCC, Segments 1, 3, 4, 5, 6

- 0 - 0

1) The guidance should be coordinated with the Supply Chain SDT. 

2) The GTB language that states: “Section 5.2: Entities are to document and implement their process(es) to mitigate the introduction of malicious code through the use of one or more of the protective measures listed.” is to prescriptive. Recommend that the “are to” be changed to “may”.  The use of prescriptive language like “should” and “are to” should be used on a very limited basis if not removed entirely.  Guidance should be shifted to a programmatic approach.

Colorado Springs Utilities, Segment(s) 5, 3, 1, 6, 5/6/2015

- 0 - 0

Jason Snodgrass, 1/24/2017

- 0 - 0

Duke Energy , Segment(s) 1, 5, 6, 4/10/2014

- 0 - 0

Illinois Municipal Electric Agency supports comments provided by the American Public Power Association.

Bob Thomas, 1/25/2017

- 0 - 0

Lan Nguyen, On Behalf of: CenterPoint Energy Houston Electric, LLC, Texas RE, Segments 1

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Aaron Austin, On Behalf of: AEP, SPP RE, RF, Segments 1, 3, 5, 6

- 0 - 0

Jeffrey DePriest, 1/25/2017

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Page 56 of the Guidelines and Technical Basis includes a section titled “Vulnerability Mitigation”; however, Requirement R2, Attachment 1, Section 5 is titled “…Risk Mitigation”.  AZPS requests clarification and consistency regarding the terms vulnerability and risk as one term is more subjective than the other.   

- 0 - 0

ITC does not agree with the proposed modification in regards to guidance provided for awareness training.  The revised guidance states "The standard drafting team does not intend for Responsible Entities to be required to maintain lists of recipients and track the reception of the awareness material by personnel". This statement is ambiguous and leaves the interpretation as to whether or not tracking of reception of awareness training is actually required to maintain compliance. The specific and direct language of "Responsible Entity is not required" should be retained, to reduce confusion and ambiguity as to if this is required for compliance and not left to the disposition of individual auditors.  ITC recommends that this specific change be struck and the original language to stand.

All other changes are acceptable.

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

David Gordon, 1/25/2017

- 0 - 0

NRG recommends correction of grammatical / spelling error: on page 57 of 62 of the Guidelines and Technical basis section for requirement 2.

• If a Responsible Entity chooses to use methods that mitigate the introduction of malicious code other than those listed, it should document at how the other method(s) meet the mitigation of the introduction of malicious code objective.

Pertaining to project 2016-02, NRG recommends that the Low Impact requirements should be incorporated into the existing CIP standards using applicability tables because this would remove inconsistencies and confusion between L/M/H and provide more efficiency within the industry. For example, applied CIP-010-2 Attachment 1 for TCA and Removable Media requirements, with the exception of the authorized user or machine lists.

Kara White, On Behalf of: NRG - NRG Energy, Inc., FRCC, MRO, WECC, Texas RE, NPCC, SERC, SPP RE, RF, Segments 3, 4, 5, 6

- 0 - 0

ACES Standards Collaborators, Segment(s) 1, 5, 3, 4, 1/25/2017

- 0 - 0

Mike Anctil, 1/25/2017

- 0 - 0

Tacoma Power supports comments submitted by APPA.

John Merrell, Tacoma Public Utilities (Tacoma, WA), 1, 1/25/2017

- 0 - 0

No comments for section 5.

 

Roger Dufresne, 1/25/2017

- 0 - 0

Melanie Seader, On Behalf of: Edison Electric Institute, NA - Not Applicable, Segments NA - Not Applicable

- 0 - 0

Si Truc Phan, On Behalf of: Hydro-Qu?bec TransEnergie, NPCC, Segments 1

- 0 - 0

Reclamation appreciates the Standards Drafting Team's consideration of prior recommendations. Reclamation agrees with the changes and has the following comment:

 

In the redline version of the Guidelines and Technical Basis, some typographical errors include:

  • The spelling of "Responsible Entities" on the sixth line of page 55.

  • A duplicate paragraph at the bottom of page 56 and the top of page 57.

  • The spelling of "to use" and "document" in the third bullet of page 57.

  • The word "is" at the beginning of a sentence on the third line from the bottom of page 57.

Wendy Center, U.S. Bureau of Reclamation, 5, 1/25/2017

- 0 - 0

Amy Casuscelli, On Behalf of: Xcel Energy, Inc. - MRO, WECC, SPP RE - Segments 1, 3, 5, 6

- 0 - 0

None.

Santee Cooper , Segment(s) 1, 5, 1/25/2017

- 0 - 0

Texas RE noticed the following:

  • Page 56, Requirement R2, Attachment 1, Section 5.1 - Transient Cyber Asset(s) Managed by the Responsible Entity states, “For Transient Cyber Assets and Removable Media that are connected to both low impact and medium/high impact BES Cyber Systems, entities must be aware of the differing levels of requirements and manage these assets under the program that matches the highest impact level to which they will connect.” Since this concept is the same as described in the Guidelines and Technical Basis of CIP-005-5, Texas Re suggests that the SDT use the same “high water mark” language found in the Guidelines and Technical basis of CIP-005-5 to stay consistent.

     

  • Page 57, Requirement R2, Attachment 1, Section 5.1 - Transient Cyber Asset(s) Managed by the Responsible Entity states, “The intent is not to require a log documenting each connection of a Transient Cyber Asset to a BES Cyber Asset.” Texas RE considers keeping a list of BES Cyber Assets as best practice and this language discourages it.  Texas RE encourages entities to have an inventory of their low impact BES Cyber Systems.

     

  • Page 57, Requirement R2, Attachment 1, Section 5.1 - Transient Cyber Asset(s) Managed by the Responsible Entity states, “If a Responsible Entity chooses touse methods….” There should be a space between “touse”.

Rachel Coyne, Texas Reliability Entity, Inc., 10, 1/25/2017

- 0 - 0

Patricia Lynch, 1/25/2017

- 0 - 0

Patricia Lynch, 1/25/2017

- 0 - 0

1) The guidance should be coordinated with the Supply Chain SDT. 

2) The GTB language that states: “Section 5.2: Entities are to document and implement their process(es) to mitigate the introduction of malicious code through the use of one or more of the protective measures listed.” is to prescriptive. Recommend that the “are to” be changed to “may”.  The use of prescriptive language like “should” and “are to” should be used on a very limited basis if not removed entirely.  Guidance should be shifted to a programmatic approach.

FMPA, Segment(s) , 12/5/2016

- 0 - 0

The information in the GTB section does not appear to be consistent with the information in Requirement R2.  Our interpretation of Requirement R2 suggests that there is not enough clarity in the Requirement to differentiate whether the focus is solely on CIP-002 and its attachment 1 or is the focus more on CIP-003-7(i) and its Attachment 1. We suggest adding clarity to the Requirement and/or the GTB to ensure that there is no confusion as to the Requirement’s intent as well as what an audit team’s interpretation of the performance of an entity during the auditing process. 

SPP Standards Review Group, Segment(s) , 1/25/2017

- 0 - 0

Southern Company, Segment(s) 1, 3, 5, 6, 8/3/2016

- 0 - 0

Two comments.

First, recommend changing “should” to “may” in this paragraph

To facilitate these controls, Responsible Entities may execute agreements with other parties to provide support services to BES Cyber Systems and BES Cyber Assets that may involve the use of Transient Cyber Assets. Entities may consider using the Department of Energy Cybersecurity Procurement Language for Energy Delivery dated April 2014.1 Procurement language may unify the other party’s and entity’s actions supporting the BES Cyber Systems and BES Cyber Assets. CIP program attributes may be considered including roles and responsibilities, access controls, monitoring, logging, vulnerability, and patch management along with incident response and back up recovery may be part of the other party’s support. Entities should consider the “General Cybersecurity Procurement Language” and “The Supplier’s Life Cycle Security Program” when drafting Master Service Agreements, Contracts, and the CIP program processes and controls.

 

Second, recommend updating 5.3 from “If malicious code is discovered, it must be removed or mitigated to prevent it from being introduced into the BES Cyber Asset or BES Cyber System.“ to “If malicious code is discovered, it must be removed or mitigated prior to connection to a BES Cyber Asset or BES Cyber Systems in order to prevent the malicious code from being introduced into the BES Cyber Asset or BES Cyber System.“

RSC no Dominion and OPG, Segment(s) 1, 0, 2, 4, 5, 6, 7, 3, 1/20/2017

- 0 - 0

- 0 - 0

Sandra Shaffer, Berkshire Hathaway - PacifiCorp, 6, 1/25/2017

- 0 - 0

The guidance should be coordinated with the Supply Chain SDT. 

Ronald Donahey, TECO - Tampa Electric Co., 3, 1/25/2017

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Hot Answers

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Other Answers

Jamie Monette, Allete - Minnesota Power, Inc., 1, 1/9/2017

- 0 - 0

RoLynda Shumpert, On Behalf of: SCANA - South Carolina Electric and Gas Co., SERC, Segments 1, 3, 5, 6

- 0 - 0

Christopher Chavez, On Behalf of: Salt River Project, WECC, Segments 1, 3, 5, 6

- 0 - 0

MRO NSRF, Segment(s) 3, 4, 5, 6, 1, 2, 1/4/2017

- 0 - 0

Bobby Olsen, Salt River Project, 6, 1/19/2017

- 0 - 0

Dennis Minton, On Behalf of: Dennis Minton, , Segments 1, 3

- 0 - 0

Sarah Gasienica, 1/19/2017

- 0 - 0

- 0 - 0

Michael Ward, 1/20/2017

- 0 - 0

Tennessee Valley Authority, Segment(s) 1, 3, 5, 6, 9/1/2016

- 0 - 0

Sean Bodkin, Dominion - Dominion Resources, Inc., 6, 1/23/2017

- 0 - 0

Ginette Lacasse, On Behalf of: Seattle City Light, WECC, Segments 1, 3, 4, 5, 6

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Ryan Olson, Portland General Electric Co., 5, 1/23/2017

- 0 - 0

Entergy cannot agree with the Implementation Plan timeline given the standard as written, and the concerns discussed in the comments submitted above. Until clarity is given regarding the scope and evidentiary requirements necessary to achieve compliance, Entergy cannot support the short implementation timeline proposed as the feasibility of implementing controls and evidenciary requirements to meet the standard as currently drafted in that small timeframe for an Entity as large as Entergy is miniscule.

Julie Hall, Entergy, 6, 1/23/2017

- 0 - 0

Daniel Gacek, Exelon, 1, 1/23/2017

- 0 - 0

Aaron Cavanaugh, On Behalf of: Bonneville Power Administration, WECC, Segments 1, 3, 5, 6

- 0 - 0

Companies with a large number of low impact assets will need this time to educate users about handling TCAs and Removable Media. These assets are categorized as low impact because they inherently have a low ability to negatively impact the Bulk Electric System. We do not want to focus our resources on rolling out this education at the expense of efforts that mitigate risks to assets that inherently have a greater ability to negatively impact the Bulk Electric System.

During the 18-month implementation plan, we will design the overall processes taking into consideration differences between different plant types (gas, lignite, combustion turbine and combined cycle). We will roll out that program to a single pilot plant to identify lessons learned and improve the experience as we onboard subsequent plants. We anticipate spending 3-5 months to design the processes and pilot the program. The remaining months will be spent rolling out to our fleet (40 units at 15 plants). The 18-month implementation plan is appropriate as it allows us to carefully and thoughtfully assign resources to most effectively and efficiently mitigate cyber risk.

Luminant, Segment(s) 6, 7, 5, 1/24/2017

- 0 - 0

While achievable in 18 calendar months, the standard needs significant improvement before a yes vote on the implementation. 

Maryclaire Yatsko, On Behalf of: Seminole Electric Cooperative, Inc., FRCC, Segments 1, 3, 4, 5, 6

- 0 - 0

None

Colorado Springs Utilities, Segment(s) 5, 3, 1, 6, 5/6/2015

- 0 - 0

Jason Snodgrass, 1/24/2017

- 0 - 0

Duke Energy agrees with the comments submitted by EEI regarding the proposed Implementation Plan.

Duke Energy , Segment(s) 1, 5, 6, 4/10/2014

- 0 - 0

Illinois Municipal Electric Agency supports comments provided by the American Public Power Association.

Bob Thomas, 1/25/2017

- 0 - 0

CenterPoint Energy agrees with EEI’s comments regarding the implementation plan for the Low Impact BES Cyber System modifications.  

Lan Nguyen, On Behalf of: CenterPoint Energy Houston Electric, LLC, Texas RE, Segments 1

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Aaron Austin, On Behalf of: AEP, SPP RE, RF, Segments 1, 3, 5, 6

- 0 - 0

Jeffrey DePriest, 1/25/2017

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

- 0 - 0

ITC Holdings agrees with the comments compiled by the EEI CIP Standards subgroup– see below:

SUMMARY:

CIP-003-6, Requirement R2, Attachment 1, sections 2 and 3 have been approved (under the Order No. 822 implementation plan) to be effective on September 1, 2018. However, in Order No. 822, the Commission ordered NERC (within 1 year) to provide clarity regarding the LERC (Low Impact External Routable Connectivity) definition, specifically ambiguity surrounding the term "direct" used in the definition. When the SDT set out to modify the definition they found that it was more appropriate to modify the requirement language to address the ambiguity. The modified standard (version 7) is expected to be filed with FERC by March 31, 2017.

CIP-003-6, Requirement R2, Attachment 1, sections 2 and 3 is effective September 1, 2018 and version 7, if FERC approves, will be effective 18 months from FERC's approval, so doing rough math (March 31, 2017 NERC filing of version 7, August 2017 NOPR--assuming ~5 months FERC review, February 2018 FERC approval--assuming 60 day notice and comment, and 3 month FERC review): version 7 would become effective around August 2019, basically a year after Version 6 (the time it took NERC to make the modification).

RATIONALE:

Reasons for supporting a change to the implementation plan: 1) retiring the implementation of CIP-003-6, attachment 1, sections 2 and 3; 2) synching up the implementation the low impact BES Cyber System modifications (attachment 1, sections 2, 3, and 5); and 3) giving entities 18 months to implement these sections:

  1. Companies will not have certainty regarding CIP-003-6 implementation until February 2018, but will have to move forward on version 6 to make the Sept. 2018 compliance deadline or accept the compliance risk by not implementing version 6.

  2. According to the Commission (Order No. 822), the CIP-003-6 modification "is necessary to provide needed clarity to the definition and eliminate ambiguity surrounding the term "direct" as it is used in the proposed definition." As a result, implementation of CIP-003-6 without the modification doesn't make much sense in light of the ambiguity identified by the Commission.

  3. Low impact BES Cyber Systems (LIBCS) have a low impact to the BES compared to medium and high impact BES Cyber Systems.

  4. LIBICS number in the tens of thousands systems; it will take time to carefully implement the new CIP-003 requirements. Implementing CIP-003-6 LERC, CIP-003-7 LERC, and then CIP-003-7 TCA in three steps will strain resources for systems with low impact to the BES. It would be more efficient to implement just the CIP-003-7 LERC and TCA modifications at the same time.

  5. Change management at this scale, will also be more effective if done all at once, which will help reduce the potential spike in audit violations.

- 0 - 0

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

David Gordon, 1/25/2017

- 0 - 0

Pertaining to project 2016-02, CIP-003-7(i), it doesn’t appear that the implementation plan accounts for additional time to implement 1.2.5 and 1.2.6. NRG recommends that the implementation plan allow for 18 months implementation time of 1.2.5 and 1.2.6. (the same implementation time as other requirements)

Kara White, On Behalf of: NRG - NRG Energy, Inc., FRCC, MRO, WECC, Texas RE, NPCC, SERC, SPP RE, RF, Segments 3, 4, 5, 6

- 0 - 0

ACES Standards Collaborators, Segment(s) 1, 5, 3, 4, 1/25/2017

- 0 - 0

Mike Anctil, 1/25/2017

- 0 - 0

John Merrell, Tacoma Public Utilities (Tacoma, WA), 1, 1/25/2017

- 0 - 0

No comments for section 6.

 

Roger Dufresne, 1/25/2017

- 0 - 0

We strongly support the Implementation Plan, which seeks to replace compliance with CIP-003-6, Requirement R2, Attachment 1, Sections 2 and 3 with compliance with CIP-003-7(i) (and CIP-003-7) such that only one implementation is required for the LIBICS modifications, 18 months from FERC approval. Our members agree with the SDT’s approach and offer further explanations as to the importance of this implementation plan:

1.      For CIP-003 alone, EEI members are looking at 3 implementation phases for a very large group of disaggregate assets (substations with variations among systems, types, shared footprints and components as well as generating stations that are extremely complex with many different systems and manufacturers involved).  LIBCS number in the tens of thousands of systems; it will take time to carefully implement the new CIP-003 requirements.  Implementing CIP-003-6 LERC, CIP-003-7 LERC, and then CIP-003-7 TCA in three steps will strain resources for systems with low impact to the BES.

2.      Change management at this scale, will also be more effective if done all at once, which will help reduce the potential spike in audit violations.  When we say more effective, we really mean doing it right for security and reliability. Training on one change for CIP-003-6 and then training again for CIP-003-7 will create confusion for field forces. Having one date to train on this culture change management would be more effective when an entity needs to train 250 plus field and engineering people regarding 550 or more low impact BES Cyber Systems. If field people are confused, they will make or may be prone to make mistakes due to confusion or rapidly changing expectations.  Potential violations will not protect against security threats or reliability issues.

3.      Shared facilities create another implementation issue. For example, an EEI member has approximately half of their low impact substations owned by third parties, shared facilities. To make each of the section 2 and 3 changes, they will have to physically go to each substation, which are owned by different entities and as a result are all different. As a result, the approaches they take at each facility must be different, which is also a good thing in the security world. Eighteen months is necessary to make these changes.

4.      The revised CIP-003-7 language including retirement of the LERC definition improves the clarity of the requirements. However, the revisions represent a change in assessment approach and will precipitate a new analysis of which locations will be in scope for section 3. The LERC definition provided a filter by the use of the word 'direct' that could be applied when determining which locations were in scope.  The retirement of LERC removed that filter. The new language replacing the LERC definition established new assessment criteria and applies it regardless of direct or indirect connectivity. The change to LERC requires Responsible Entities to perform a new analysis of each of their locations. Applying the CIP-003-7 requirements means that entities must walk down each location in scope to determine the specific configurations (physical and electronic) that exist at the location.  These walk downs are currently underway to apply a -6 implementation focused on the definition of LERC from CIP-003-6. The scope of analysis will change under CIP-003-7, so that all locations must be assessed for connectivity and then assessed against the new criteria.

Melanie Seader, On Behalf of: Edison Electric Institute, NA - Not Applicable, Segments NA - Not Applicable

- 0 - 0

Si Truc Phan, On Behalf of: Hydro-Qu?bec TransEnergie, NPCC, Segments 1

- 0 - 0

Wendy Center, U.S. Bureau of Reclamation, 5, 1/25/2017

- 0 - 0

Amy Casuscelli, On Behalf of: Xcel Energy, Inc. - MRO, WECC, SPP RE - Segments 1, 3, 5, 6

- 0 - 0

None.

Santee Cooper , Segment(s) 1, 5, 1/25/2017

- 0 - 0

Texas RE does not necessarily object to the SDT’s proposed 12-month implementation period.  However, Texas RE respectfully requests that the SDT provide a basis for its decision to adopt such a 12-month compliance window, including any data it considered in determining that this was an appropriate window for affected entities to meet their compliance obligations under the revised Standards.

Rachel Coyne, Texas Reliability Entity, Inc., 10, 1/25/2017

- 0 - 0

Patricia Lynch, 1/25/2017

- 0 - 0

Patricia Lynch, 1/25/2017

- 0 - 0

FMPA, Segment(s) , 12/5/2016

- 0 - 0

We suggest the drafting team include the approval of the RSAW into the Implementation Plan as this is a significant and related document. 

SPP Standards Review Group, Segment(s) , 1/25/2017

- 0 - 0

The majority of actions necessitating the timeframe proposed in the Implementation Plan modifications involve identifying and implementing the physical, electronic, and TCA/RM controls necessary for over 1200 assets containing Low Impact BES Cyber Systems, as well as training a massive amount of personnel on meeting and maintaining compliance with these new Standard requirements.  Although the requirements themselves may be less rigid than those for Highs and Mediums, the proposed implementation timeframe is required from a volume standpoint, as well as from a risk-based standpoint so as not to divert attention and resources away from meeting and maintaining compliance on all of the other High and Medium risk assets

Southern Company, Segment(s) 1, 3, 5, 6, 8/3/2016

- 0 - 0

RSC no Dominion and OPG, Segment(s) 1, 0, 2, 4, 5, 6, 7, 3, 1/20/2017

- 0 - 0

- 0 - 0

Sandra Shaffer, Berkshire Hathaway - PacifiCorp, 6, 1/25/2017

- 0 - 0

Ronald Donahey, TECO - Tampa Electric Co., 3, 1/25/2017

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Hot Answers

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Other Answers

Jamie Monette, Allete - Minnesota Power, Inc., 1, 1/9/2017

- 0 - 0

RoLynda Shumpert, On Behalf of: SCANA - South Carolina Electric and Gas Co., SERC, Segments 1, 3, 5, 6

- 0 - 0

Christopher Chavez, On Behalf of: Salt River Project, WECC, Segments 1, 3, 5, 6

- 0 - 0

Small entities will not be able to go up against a vendor (i. e. Micro Soft in size) and request to review their most current protections to comply with section 5.2.  The above clarity will assure we meet the attributes of 5.2.  The NSRF does not wish for CIP-003-7(i) to be the number one non compliance Standard going forward in NERC, similar to CIP-007-6.

MRO NSRF, Segment(s) 3, 4, 5, 6, 1, 2, 1/4/2017

- 0 - 0

Bobby Olsen, Salt River Project, 6, 1/19/2017

- 0 - 0

Dennis Minton, On Behalf of: Dennis Minton, , Segments 1, 3

- 0 - 0

Sarah Gasienica, 1/19/2017

- 0 - 0

Entities are increasing their use of malicious code mitigation using tools such as Cylance, which does not rely on signatures or updates.  The measures should consider these tools and provide examples of evidence that will prove compliance.

- 0 - 0

Michael Ward, 1/20/2017

- 0 - 0

Tennessee Valley Authority, Segment(s) 1, 3, 5, 6, 9/1/2016

- 0 - 0

Dominion recommends that the first VSL conditional statement for Requirement 1 Part 1.2 (page 14 of 62 of draft 1 of CIP-003-7(i)) be consistent with the prior version of CIP-003 and read as follows:

 

Lower VSL:  The Responsible Entity documented one or more cyber security policies for its assets identified in CIP-002 containing low impact BES Cyber Systems, but did not address two or fewer of the six topics required by R1. (R1.2)

Moderate VSL: The Responsible Entity documented one or more cyber security policies for its assets identified in CIP-002 containing low impact BES Cyber Systems, but did not address three of the six topics required by R1. (R1.2)

High VSL: The Responsible Entity documented one or more cyber security policies for its assets identified in CIP-002 containing low impact BES Cyber Systems, but did not address four of the six topics required by R1. (R1.2)

Severe VSL: The Responsible Entity documented one or more cyber security policies for its assets identified in CIP-002 containing low impact BES Cyber Systems, but did not address five or more of the six topics required by R1. (R1.2)

 

The revised VSLs accurately reflect the actual severity when a failure to address the appropriate topics occurs.

Sean Bodkin, Dominion - Dominion Resources, Inc., 6, 1/23/2017

- 0 - 0

Seattle City Light has additional concerns that led it to vote NO for this ballot. One concern is about new sub-part 1.2.6, which introduces CIP Expectional Circumstances to Low impact facilities. The other concern is about seeming errors in the Violation Severity Level (VSL) tables for some of the new parts and sections introduced in CIP-003-7(i).

Regarding sub-part 1.2.6, Seattle supports the concept of allowing CIP Exception Circumstances for Low impact facilities and related requirements, and find this idea highly sensible and reasonable. Seattle is concerned, however, that the change appeared without notice or discussion in the present draft of CIP-003-7(i), and that the application of CIP Expectional Circumstances for Lows is not at all defined. In particular, other Standards, parts, and sub-parts of CIP version 5/6 explicitly identify where CIP Exceptional Circumstances are allowed. This explicit mention creates the presumption that CIP Exceptional Circumstances are allowed only for said Standards, parts, or sub-parts; some auditors have stated as such. Seattle is aware that an drafting team effort is planned to address inconsistencies in the existing application of CIP Exceptional Circumstances, and finds it premature to expand the use of CIP Exceptional Circumstances in a way that introduces even more uncertainty—how are they applied to Lows where no existing Low Standard mentions that CIP Expectional Circumstances are allowed—before the existing issues are addressed. That the concept was introduced without discussion or technical guidance language only heightens our concern. As a possible corrective, Seattle recommends that the Part R2 of CIP-003-7(i) be modified as follows (BOLD text is new):

R2. Each Responsible Entity with at least one asset identified in CIP-002 containing low impact BES Cyber Systems shall, EXCEPT FOR CIP EXCEPTIONAL CIRCUMSTANCES, implement one or more documented cyber security plan(s) for its low impact BES Cyber Systems that include the sections in Attachment 1.

 

Regarding the VSL tables, Seattle does not understand the difference among the Lower, Moderate, and High VSLs for failure to perform some or all of the activities according for Requirement R2, Attachment 1, Section 5.1. For Transient Cyber Assets, the Lower VSL states:

The Responsible Entity documented its plan(s) for Transient Cyber Assets and Removable Media, but failed to manage its Transient Cyber Asset(s) according to Requirement R2, Attachment 1, Section 5.1. (R2)

 

The applicable Moderate VSL states:

The Responsible Entity documented its plan(s) for Transient Cyber Assets and Removable Media, but failed to document mitigation for the introduction of malicious code for Transient Cyber Assets managed by the Responsible Entity according to Requirement R2, Attachment 1, Sections 5.1 and 5.3. (R2)

 

And the applicable High VSL reads:

The Responsible Entity documented its plan(s) for Transient Cyber Assets and Removable Media, but failed to implement mitigation for the introduction of malicious code for Transient Cyber Assets managed by a party other than the Responsible Entity according to Requirement R2, Attachment 1, Section 5.2. (R2)

Seattle does not understand the difference among the three items, given that the failure to manage according to plan (the Lower VSL) means that introduction of mitigation code is not documented (the Moderate VSL) and/or mitigated (High VSL); there are not other applicable activities to fail. As such, Seattle recommends these be consolidated into a single VSL at the Moderate (or perhaps High) level.

 

Finally, Seattle also finds confusing the wording in the Lower VSL for Removable Media. For Transient Cyber Assets this VSL states:

The Responsible Entity documented its plan(s) for Transient Cyber Assets and Removable Media, but failed to document the Removable Media section(s) according to Requirement R2, Attachment 1, Section 5.3. (R2)

 

Seattle does not understand how an entity can ever meet the Lower VSL for Removable Media, in that to do so it must “document its plan(s) for…Removable Media but fail to document the Removable Media section(s) according to Requirement 2.” As best as we understand, the Removable Media Plans are the Removable Media sections of Requirement 2, so the statement appears to be in error. As a corrective, Seattle suggests that the Lower VSL entry for Removable Media be modified to mirror that of Transient Cyber Assets, and thus read (BOLD indicates where “Removable Media” was substituted for Transient Cyber Asset):

The Responsible Entity documented its plan(s) for Transient Cyber Assets and Removable Media, but failed to manage its REMOVABLE MEDIA according to Requirement R2, Attachment 1, Section 5.1. (R2)

Ginette Lacasse, On Behalf of: Seattle City Light, WECC, Segments 1, 3, 4, 5, 6

- 0 - 0

none

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

Ryan Olson, Portland General Electric Co., 5, 1/23/2017

- 0 - 0

Julie Hall, Entergy, 6, 1/23/2017

- 0 - 0

Daniel Gacek, Exelon, 1, 1/23/2017

- 0 - 0

BPA respectfully suggests spellchecking the redline before finalizing.  For example:

Page 33: Entiteis

Page 57: Transiet

Aaron Cavanaugh, On Behalf of: Bonneville Power Administration, WECC, Segments 1, 3, 5, 6

- 0 - 0

Luminant, Segment(s) 6, 7, 5, 1/24/2017

- 0 - 0

None

Maryclaire Yatsko, On Behalf of: Seminole Electric Cooperative, Inc., FRCC, Segments 1, 3, 4, 5, 6

- 0 - 0

1) The word “and” should be added at the end of R1.2.5

 

2) This comment form did not reference the addition of CIP Exceptional Circumstances as Requirement R1.2.6 and the inclusion of the phrase “except under CIP Exceptional Circumstances” in Attachment 1, Section 5.  The “except under CIP Exceptional Circumstances” phrase should also be addressed in Attachment 1 Sections 2 and 3.  Not addressing CEC in Sections 2 and 3 may result in a “no” vote for on future ballot of this standard.

3) A Section 6 under Attachment 2 is needed to explain how the CIP Exceptional Circumstance is to be used so you can put it into your policy/plan accordingly.

Colorado Springs Utilities, Segment(s) 5, 3, 1, 6, 5/6/2015

- 0 - 0

Jason Snodgrass, 1/24/2017

- 0 - 0

Duke Energy , Segment(s) 1, 5, 6, 4/10/2014

- 0 - 0

Illinois Municipal Electric Agency supports comments provided by the American Public Power Association.

Bob Thomas, 1/25/2017

- 0 - 0

Lan Nguyen, On Behalf of: CenterPoint Energy Houston Electric, LLC, Texas RE, Segments 1

- 0 - 0

none

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

no

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

none

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

None

Aaron Austin, On Behalf of: AEP, SPP RE, RF, Segments 1, 3, 5, 6

- 0 - 0

None

Jeffrey DePriest, 1/25/2017

- 0 - 0

none

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

- 0 - 0

ITC Holdings agrees with the comment submitted by NSRF – see below:


Small entities will not be able to go up against a vendor (i. e. Micro Soft in size) and request to review their most current protections to comply with section 5.2.  The above clarity will assure we meet the attributes of 5.2.  The NSRF does not wish for CIP-003-7(i) to be the number one non compliance Standard going forward in NERC, similar to CIP-007-6.

- 0 - 0

no

Karie Barczak, On Behalf of: DTE Energy - Detroit Edison Company, , Segments 3, 4, 5

- 0 - 0

David Gordon, 1/25/2017

- 0 - 0

Kara White, On Behalf of: NRG - NRG Energy, Inc., FRCC, MRO, WECC, Texas RE, NPCC, SERC, SPP RE, RF, Segments 3, 4, 5, 6

- 0 - 0

  1. The inclusion of CIP Exceptional Circumstance for lows adds additional compliance burden above and beyond the FERC Directives. This will require Cyber Security Policy revisions, training and increase audit risk for lows who have not seen any addtioal risks to the BES to require CIP Exceptional Circumstances as part of their CIP cyber Security Program.
  2. If a low impact entity connects an identified 30-day TCA beyond the thirty days, what is the classification of the asset? If this was a high or medium impact entity, the TCA would be classified as a Protected Cyber Asset (PCA).  However, PCAs are not applicable to low impact entities, as a low impact’s TCA would not be classified as a BES Cyber Asset that could impact the BES within 15 minutes.  Would the low impact entity who failed to connect the TCA within the thirty day timeframe  have to self-report the TCA to Regional Entities?  If so, this would impose a greater violation risk for lows than for high and medium impact entities.
  3. We thank the SDT for this opportunity to provide comments.

ACES Standards Collaborators, Segment(s) 1, 5, 3, 4, 1/25/2017

- 0 - 0

Mike Anctil, 1/25/2017

- 0 - 0

Tacoma Power supports comments submitted by APPA.

John Merrell, Tacoma Public Utilities (Tacoma, WA), 1, 1/25/2017

- 0 - 0

No comments for section 7.

 

Roger Dufresne, 1/25/2017

- 0 - 0

Melanie Seader, On Behalf of: Edison Electric Institute, NA - Not Applicable, Segments NA - Not Applicable

- 0 - 0

Some typos:

P 55: 'entiteis'

P 70 of 75: “touse”; “. is the SDT”; “toTransiet Cyber Assets”

Si Truc Phan, On Behalf of: Hydro-Qu?bec TransEnergie, NPCC, Segments 1

- 0 - 0

Wendy Center, U.S. Bureau of Reclamation, 5, 1/25/2017

- 0 - 0

Xcel Energy supports the comments of the Edison Electric Institute.

Amy Casuscelli, On Behalf of: Xcel Energy, Inc. - MRO, WECC, SPP RE - Segments 1, 3, 5, 6

- 0 - 0

The CIP Exceptional Circumstance concept does not belong with the Low Impact requirements.  The purpose of CIP-007-3i was to define and create requirements for Transient Cyber Assets and Removable Media.  The need for Exceptional Circumstances for High and Medium is because the Standard mandates a PRA for unescorted access.  Even with Exceptional Circumstances you have to report a violation because of the externally mandated PRA.  In the case of Low Impact, the entity writes the requirements for access.  Most departments responsible for physical security automatically allow the entrance of Emergency Personnel and Police if there is an alarm or 911 call.  This could be written into each Responsible Entity's Low Impact Cyber Security Policy (CIP-003 R1.2) but that doesn't seem to support BES Reliability. 

Santee Cooper , Segment(s) 1, 5, 1/25/2017

- 0 - 0

Texas RE notes some possible issues with the proposed Violation Severity Levels associated with the proposed additions to CIP-003, Attachment 1.  First, the second proposed “Lower VSL” provides that “[t]he Responsible Entity documented its plan(s) for Transient Cyber Assets and Removable Media, but failed to document the Removable Media sections according to Requirement R2, Attachment 1, Section 5.3.”  Although it is possible to read the VSL language as referring first to general documentation for TCAs and Removable Media and then to the two specific Removable Media elements identified in Section 5.3, this connection could be made clearer.  One approach would be revise the Lower VSL to read “The Responsible Entity documented its plan(s) for Transient Cyber Assets and Removable Media, but failed to document the use of method(s) to detect malicious code on Removable Media using a Cyber Asset other than a BES Cyber System or mitigation of the threat of detected malicious code on Removable Media prior to connecting Removable Media to a low impact BES Cyber System.”

 

Second, and related to the first issue above, the initial additional “Moderate VSL” provides that the Responsible Entity documented its plan(s) for Transient Cyber Assets and Removable Media, but failed to document mitigation for the introduction of malicious code for Transient Cyber Assets managed by the Responsible Entity according to Requirement R2, Attachment 1, Sections 5.1 and 5.3.”  (emphasis added).  However, Section 5.3 applies to Removable Media and not TCAs.  As such, the reference here seems inappropriate and potentially conflicts with the “Low VSL” for documentation of Removable Media mitigation described above.  Texas RE recommends that the SDT either eliminate the reference to Section 5.3 here, or develop a new “Moderate VSL” applicable to the mitigation requirements for Removable Media in Section 5.3.  The Standard Drafting Team should further ensure that this approach is consistent with the “Low VSL” for Removable Media documentation as well.

 

Finally, while Texas RE does not necessarily object to the general VSL assignments at this time, Texas RE respectfully requests that the SDT provide a basis for its decisions to assign VSL categories to the various elements.  In particular, Texas RE would like to understand the SDT’s decision to assign “Low” and “Moderate” VSL categories to Removable Media and “Moderate” and “High” VSL categories to Transient Cyber Assets.

Rachel Coyne, Texas Reliability Entity, Inc., 10, 1/25/2017

- 0 - 0

Patricia Lynch, 1/25/2017

- 0 - 0

Patricia Lynch, 1/25/2017

- 0 - 0

1) The word “and” should be added at the end of R1.2.5

2) This comment form did not reference the addition of CIP Exceptional Circumstances as Requirement R1.2.6 and the inclusion of the phrase “except under CIP Exceptional Circumstances” in Attachment 1, Section 5.  The “except under CIP Exceptional Circumstances” phrase should also be addressed in Attachment 1 Sections 2 and 3.  Not addressing CEC in Sections 2 and 3 may result in a “no” vote for on future ballot of this standard.

3) A Section 6 under Attachment 2 is needed to explain how the CIP Exceptional Circumstance is to be used so you can put it into your policy/plan accordingly.

FMPA, Segment(s) , 12/5/2016

- 0 - 0

N/A

SPP Standards Review Group, Segment(s) , 1/25/2017

- 0 - 0

Southern Company, Segment(s) 1, 3, 5, 6, 8/3/2016

- 0 - 0

RSC no Dominion and OPG, Segment(s) 1, 0, 2, 4, 5, 6, 7, 3, 1/20/2017

- 0 - 0

To address the changes to the RSAW provided on January 20th Under the Note to Auditor section, Attachment 1, Section 3:

Bullet 1: Recommended to state that “the devices used to control electronic access” can be documented at a representative level.  The standard (Attachment 1, Section 3, Bullet 1) under examples of evidence state that documentation can be “at each asset or group of assets containing low impact BES Cyber Systems” level and can be representative diagrams, meaning a list of devices at each asset is not required under the standard and puts additional documentation burden on the Entity as currently worded in the RSAW.

Bullet 2: Recommended to document necessary inbound and outbound routable protocols communications at a standard level versus at each asset (e.g. document SCADA communications as necessary inbound and outbound for the Entities entire system, rather than having to document at each asset) for same reason as our comment for Bullet 1.

Bullet 3 and 4: Recommended to document that the electronic access controls can be provided at a standard level (e.g. standard configurations) which would apply to the standard devices, versus providing per asset.

- 0 - 0

PacifiCorp supports comments submitted by EEI.

Sandra Shaffer, Berkshire Hathaway - PacifiCorp, 6, 1/25/2017

- 0 - 0

1) This comment form did not reference the addition of CIP Exceptional Circumstances as Requirement R1.2.6 and the inclusion of the phrase “except under CIP Exceptional Circumstances” in Attachment 1, Section 5.  The “except under CIP Exceptional Circumstances” phrase should also be addressed in Attachment 1 Sections 2 and 3. 

 

Ronald Donahey, TECO - Tampa Electric Co., 3, 1/25/2017

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0

Glen Farmer, On Behalf of: Avista - Avista Corporation, , Segments 1, 3, 5

- 0 - 0